Laskin Road Corridor Project (AT-112-1 and AT-112-2)
HRSD is undertaking a major project to replace approximately 2.7 miles of its Hilltop / Point O' Woods Interceptor Force Main, which is located in the Laskin Road Corridor of Virginia Beach. We've created this web site to provide current information about the project and its benefits. We will update and expand the content as the project progresses.
You may send your questions, comments, suggestions, or complaints to Project E-mail. An HRSD representative will respond as soon as possible.
TRAFFIC ADVISORY: June 30, 2011 - July 7-22 Lane Closure Planned for Laskin Road Near Regency Hilltop (pdf)
PROJECT NEWS: June 30, 2011
The Hilltop / Point O' Woods Interceptor Force Main Replacement project will take place in east-central Virginia Beach, north of Interstate 264 between Great Neck Road and Fremac Drive, as shown on the map below. The alignment for this project is generally described as extending: A) eastward from the intersection of Great Neck Road and the Virginia Beach Boulevard/Laskin Road split, along the north side of Laskin Road to Victor Road; B) from the northwest quadrant of the Victor Road and Laskin Road intersection southward across Laskin Road and along the west side of Village Drive to Donna Boulevard; C) turning eastward along Donna Boulevard, across First Colonial Road, to the end of Donna Drive, crossing private property to Winwood Drive; D) turning south along the west side of Winwood Drive to Reynard Drive; E) turning eastward along Reynard Drive; and, F) ending at Fremac Drive.

Construction Activities (estimated dates of work appear in parentheses)
![]() |
Construction crews will begin installation of concrete pavement along the far right west bound travel lane of Laskin Road, between Hilltop Road and Bratten Avenue, starting July 7. The work schedule, which is subject to change due to weather conditions, calls for lane closures in this area through July 22. Traffic Impact: Workers and equipment will be present along the roadway during the stated times. The service road will be open throughout this pavement restoration project, and at least one access to the businesses in Regency Hilltop Shopping Center (off Regency Drive) will be maintained at all times. Appropriate signage and traffic control devices will be provided for all temporary detours and lane closures, and all areas will be adequately secured for the safety of workers and the surrounding community. For more information, please refer to the Traffic Advisory (pdf). |