Schedule
| Preliminary Design: | August 2006 - October 2007 |
| Final Design and Bidding: | Contract A: March 2007 - April 2008 |
| Contract B: July 2009 - December 2010 | |
| Contract C: August 2010 - May 2012 | |
| Construction: | Contract A: May 2008 - March 2011 |
| Contract B: January 2011 - October 2013 | |
| Contract C: June 2012 - December 2016 |