-
“Diamond Springs Sewer Replacement”
Western Trunk Force Main Replacement and Newtown Road Interceptor Force Main Relocation
HRSD Capital Improvement Program Projects (CE011700) and (CE010520) -
HRSD, your regional wastewater utility, is undertaking a project to transfer the flow from an aging sanitary sewer pipeline in the Diamond Springs Road area of Virginia Beach to a nearby HRSD sewer pipeline. Once the transfer of flow is complete, the aging sanitary sewer pipeline will be filled with cementitious material and inline valves and related components will be constructed to provide additional isolation of the nearby existing pipeline system in case of any emergencies.
Project Cost: Approximately $6,500,000
-
Notices
February 2021 - Construction Notice #1 (Revised)
November 2020 - Notice to Neighbors
-
March 2, 2021
The work at Diamond Springs Road and Bayside Road is complete. Work at Project Work Area 3 has begun near the intersection of Diamond Springs Road and Northampton Boulevard in the median. One portion of work will occur across the ramp on Diamond Springs Road to turn right onto Northampton Boulevard. The scheduled dates for the work on the ramp are February 26th, 27th and 28th and March 5th, 6th, and 7th. Traffic control measures and a detour will be in place. Work is weather and situation dependent, and dates are subject to change.
-
The work will be completed within four general locations within the right-of-way. These locations include the following intersections: Diamond Springs Road and Aragon Drive; Diamond Springs Road and Bayside Road; Diamond Springs Road and Northampton Boulevard; and Wesleyan Drive and Virginia Tech Trail. Comprehensive traffic control plans will be implemented to minimize inconvenience.
-
- Staging:
-
September 2020
- Construction:
-
Fall 2020 - Winter 2021
- Restoration:
-
Immediately following construction.
-
-
This project is a necessary part of a larger, federally mandated program to abandon aging sanitary sewer pipelines that are at risk of failure. Upgrade of the HRSD system includes transfer of flow to a nearby sanitary sewer line and installation of inline valves and related components to provide additional isolation within the nearby existing pipeline in case of any pipe failures. This project will provide updated infrastructure that will help ensure HRSD’s ability to protect public health and the environment for decades to come.
-
Comprehensive traffic control plans will be implemented to minimize disruptions to the flow of traffic. There will be planned detours during some phases of construction. Signage will be placed prior to these detours.
-
The contractor will ensure that emergency vehicle and resident access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services should not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
The work on Diamond Springs Road at the Aragon Drive and Bayside Road intersections will typically take place overnight and on weekends. Work at the westbound ramp from Diamond Springs Road to Northampton Boulevard and work on Wesleyan Drive at Virginia Tech Trail will typically take place during the day between 7 a.m. and 7 p.m. However, there may be times when extended hours, work at night, or weekend work may be necessary at these locations as well.
-
There should be no interruptions to water or sewer service throughout the duration of this project.
-
Where sewer pipeline is being installed or exposed, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, etc. should be anticipated.
-
Although the majority of the materials will be stored off-site, the contractor will need to keep some supplies within the active work zone, in the public right-of way.
-
Construction workers will not be allowed to park their personal vehicles in the public right-of-way. However, parking may occur on side streets where parking is permitted. Work trucks will be allowed to park within the active work zone.
-
The estimated cost for the project is estimated at approximately $6.5 million and is financed by the wastewater treatment fees paid by HRSD customers.
-
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status.
FootnoteIf you have any questions, concerns or comments about the project, please feel free to contact:
Lisa Bolen, HRSD Public Information Specialist, at 757.460.7000 or lbolen@hrsd.com -
- Public Information Specialist:
- Lisa Bolen 757.460.7000 (Office)
- Project Manager:
- Phil Hubbard, PE
- Additional Information:
- Projects@hrsd.com
-
- Director of Communications:
- Leila Rice, APR 757.460.7056 (Office) 757.642.1321 (Cell)
-
- Engineering Consultant Firm:
-
AECOM Technical Services, Norfolk, VA
- Engineering Consultant Project Lead:
-
William Gibson
- Contractor:
-
TBD
- City of Virginia Beach Contact:
-
Alex Swafford