Surry Hydraulic Improvements and Force Main Installation

Body

 

HRSD, your regional wastewater treatment utility, is planning sanitary sewer system improvements to your community. The entire project includes pipelines, new pump stations, and a storage tank. The pipelines and pump stations will bring sewage flows generated in the Town of Surry and vicinity to the existing HRSD pipe located in Smithfield. The existing Town Wastewater Treatment Plant will be replaced with a new pump station. A storage tank will be placed at the existing pump station at the Surry West Industrial Park, and that existing pump station will be upgraded. The pipeline will be located along the road in existing right-of-ways and easements. The Contractor will maintain a clean worksite and minimize traffic disruption. The answers to some Frequently Asked Questions (FAQs) are provided here

Project Overview
The project includes three sections and is located in Surry and Isle of Wight Counties and the Town of Smithfield. The first section includes installation of a new pump station at the current Town of Surry Wastewater Treatment Plant site at the end of Connie Drive and a buried pipeline from the treatment plant, along Rolfe Highway, to the intersection of Rolfe Highway and Colonial Trail West. The second section includes installation of a buried pipe and begins at Marina Drive to the northern edge of town and is located along Rolfe Highway. The third section includes buried pipes and pump stations and begins at the Surry West Industrial Park and is located along the Dominion Energy Easement between the Surry West Industrial Park and Colonial Trail East and along Colonial Trail East and Route 10 Business to Smithfield. Pump stations will be located at the Surry West Industrial Park, near Colonial Trail East and along Route 10 Business.

Project Schedule
Construction: Phase 1 - Town of Surry Pipelines and Pump Station: Fall 2019 – Spring 2020.
Phase 2 - Surry County Pipelines and Pump Stations: Spring 2020 – Fall 2020
Phase 3 - Isle of Wright County Pipelines and Pump Station:
Fall 2020 – Early Winter 2022.
Phase 4 - Demolition of the existing Wastewater Treatment Plant:
Early Winter 2022 – Spring 2022.
Restoration: Immediately following construction

You also may visit www.hrsd.com/construction-status for additional information and project updates.

If you have any questions, concerns or comments about the project, please feel free to contact Lisa Bolen, HRSD Public Information Specialist, at 757.460.7000 or lbolen@hrsd.com.

Thank you for your support of this effort to help achieve HRSD's vision: Future generations will inherit clean waterways and be able to keep them clean.