This project is a necessary to increase operational flexibility and system reliability of HRSD’s sewage collection system. This project will provide updated infrastructure that will help ensure HRSD’s ability to protect public health and the environment for decades to come.
-
Disruptions to traffic will be minimized. Lane closures will be required along the west bound lanes of Jefferson Avenue for a short duration of the project. Lane closures along Jefferson Avenue will occur only during nighttime hours.
-
The contractor will ensure that access to businesses will be maintained throughout construction.
-
Work will typically take place Monday through Friday during daylight hours (7 a.m. - 4 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
-
There are no plans for any interruptions to water or sewer service as a part of this project. If there are any changes, the contractor will notify you before the service interruption so you can plan appropriately. Sewer and water service typically will be restored within several hours.
-
Where sewer pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, etc. should be anticipated.
-
The contractor has negotiated with a private property owner for a storage area in the project vicinity, and this site will be used for most of the equipment and supplies. The contractor will keep some supplies within the active work zone, in the public right-of way.
-
Construction workers will not be allowed to park their personal vehicles on the public streets. However, work trucks will be allowed to park within the active work zone.
-
The estimated cost for the project is $2.7 million and is financed by the wastewater treatment fees paid by HRSD customers.
-
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the project.