“King William Central Crossing Pump Station Rehabilitation”
King William Central Crossing Pump Station Rehabilitation (MP015300) -
HRSD, your regional wastewater treatment utility, is undertaking a project to rehabilitate the King William Central Crossing Pump Station located at 123 Central Crossing Terrace, that is nearing the end of its useful life. Rehabilitating the existing pump station with new modernized infrastructure will improve the systems performance and optimize HRSD’s ability to protect public health and the environment for decades to come.
Project Cost: Approximately $2.3 Million
-
November 5, 2025
Construction has not started.
-
The work will be confined to HRSD property and the public right-of-way; construction traffic will be entering and exiting the site on Central Parkway and Central Crossing Terrace.
-
- Staging:
-
Fall 2024
- Construction:
-
Late 2025 - Summer 2026
- Restoration:
-
Immediately following construction when seasonably appropriate.
-
-
This project will provide infrastructure improvements that will help ensure HRSD’s ability to protect public health and the environment for decades to come.
-
We look at several sites to determine what meets HRSD’s needs of availability, price, property agreement terms, ease of access to the property for construction and future maintenance. Rehabilitation of the existing station was determined to be the best option.
-
Disruptions to traffic will be minimized and no planned detours are necessary, but flagging will be used to help direct traffic as needed.
-
The contractors will ensure that access to residents will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
Work will typically take place Monday through Friday during daylight hours (7 a.m. - 5 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
-
Your water and sewer services should not be affected by this project.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
Typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, and associated activities should be anticipated.
-
General construction materials will be stored onsite including piping, equipment, stone, and other materials so it is readily available by the Contractor for installation.
-
Construction workers will park onsite and in the public right-of-way near the project area. They will not be permitted to park in areas impacting access to properties or resulting in impacts to routine services like mail delivery.
-
The estimated cost for the project is approximately $2.1 million and is financed by the wastewater treatment fees paid by HRSD customers.
-
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the project.
-
- Public Information Specialist:
-
Shawn Maxfield
757.833.7483 (Office)
- HRSD Project Manager:
- Donald Jennings, PE
- Additional Information:
-
Projects@hrsd.com
-
- Chief of Communications:
-
Leila Rice, APR
757.460.7056 (Office)
-
- Onsite Inspector (Immediate/Emergent Concerns):
-
TBD
- Engineering Consultant Firm:
-
Rummel, Klepper, & Kahl, LLP Virginia Beach, VA
- Engineering Consultant Project Lead:
-
Ryan Delo, PE
- Contractor:
-
TBD
- Contractor Field Project Manager:
-
TBD
- King William County Contact:
-
Sherry Graham (Planning)