May 3, 2025
Biosolids Hauling: HRSD continues hauling biosolids from the plant site in the early morning. Additionally, the annual spring time hauling of biosolids out of the Atlantic Treatment Plant will begin. You may notice the smell of biosolids as the trucks pass through the area. We apologize for the odors that may occur, and we thank you for your patience.
Prior to trucks leaving the plant site, HRSD will ensure:
- Trucks are not overfull
- Truck beds are properly covered and sprayed
- Truck tires are clean
Long Term Improvements:
- Digester Covers –The engineer confirmed the new digester covers will be concrete construction, which will provide a more robust seal between the cover and the tank. The team is still on track with the expedited schedule. HRSD needs to have two digesters online for daily operations. The construction of the covers on the first two digesters is expected to be completed in 2026. The remaining two digesters will then be taken offline and the covers are expected to be installed in 2027.
- Solids Processing Improvements –The engineer completed the first detailed design submittal in March. HRSD is reviewing and providing comments in April. Schedule is still on track for construction completion in Summer 2028.
- Long-Term Odor Facilities – The engineer completed the first detailed design submittal in March. HRSD is reviewing and providing comments in April. Schedule is still on track for construction completion Summer 2028.
Emergency and Near-Term Improvements:
- Storage Pads Odor Neutralization System (Sprayers) – Complete
- Odor Control Station (OCS) D & B Optimizations – Complete
- Odor Control Stations capture odorous air from different parts of the plant. Plant staff will continually maintain, monitor, and optimize these systems.
- Staff also continuously monitors the plant site using a handheld odor meter to pinpoint problems as quickly as possible.
Early Work Packages (for Carbon Treatment, Digester Mixer, and Enclosed Flare):
Design is underway with early equipment procurement expected in Spring 2025. Construction completion is expected in early 2027.
- New Polishing Scrubber System (Carbon Treatment) – Carbon units have arrived, and there is an executed contract allowing the contractor to proceed with work. Underground utility investigation were conducted in late March to verify location of the gas line that needs to be relocated for this construction.
- Digester Mixer Replacement – Bids for the equipment were at the end of March. Bid review and selection will take place in April. Construction completion is still expected in early 2027.
- New Enclosed Flare – Bids for the equipment were received at the end of March. Bid review and selection will take place in April. Construction completion is still expected in Spring 2026.
Atlantic Treatment Plant Access Road:
This project has a couple of new developments that are impacting the schedule:
- The Navy is requiring a new environmental assessment beyond the ECP already completed by HRSD; HRSD must now do a Phase 1 Environmental Site Assessment (ESA). HRSD is procuring a contract to perform this assessment.
- Navy workforce challenges are slowing down the Navy’s response for reviews and approvals needed for the project.
HRSD remains optimistic that we will begin detailed design work this Spring after the Navy approves the environmental assessments.
Note: All dates are approximate as HRSD strives to bring on these new processes, procure new equipment, and install in the most efficient and productive way for our rate payers. Long lead times are expected on most equipment after purchase.