Project Introduction - October 2025
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, will begin work to rehabilitate a sanitary sewer pipeline along Waltham Drive. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, will begin work to rehabilitate manholes along Indian River Road and Ford Drive. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work is being done to resolve capacity, operational, and maintenance issues that currently affect the existing pump station and pipes that are near the end of their useful life. The work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday and could include weekend work.
--Ferebee Pump Station Concrete Pour Update--

--SUFFOLK--
Smoke testing of the sanitary sewer system will take place in your neighborhood in Suffolk in October.
November 17 - November 28, 2025
--CHESAPEAKE--
Smoke testing of the sanitary sewer system will take place in your neighborhood in Chesapeake in October.
November 10 - November 21, 2025
(This schedule is situation and weather dependent)
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, is undertaking a project to inspect and perform maintenance on the sanitary sewer piping within the intersection of Kempsville Road and Beaufain Boulevard / Brandon Boulevard. This work will start at 9:00 p.m. on Friday (10/17) and is expected to be complete by 5:00 p.m. on Sunday (10/19).
--Sewer Pipe Installation to Begin--
HRSD, your regional wastewater treatment utility, will begin work to install microtunnel pits in the Virginia Ham Drive/Portsmouth Boulevard area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, will begin work to replace sewer pipe and manholes in South Main Street and south of Bainbridge Boulevard. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.