Construction Notice Update #13 for the City of Norfolk - February 2026
-Temporary Road Closure Notice: Monroe Place Between Rockbridge and Magnolia Avenue-
-Temporary Road Closure Notice: Monroe Place Between Rockbridge and Magnolia Avenue-
--Manhole Frame Replacement Work on Great Bridge Boulevard--
HRSD, your regional wastewater treatment utility, is nearly finished with the sanitary sewer pipeline project. Remaining work includes the replacement of frames and covers on Manholes along Great Bridge Boulevard, followed by paving of the area when warmer weather is consistent. This manhole frame work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.
"Cedar Lane & Peake Lane Sewer Improvements"
Western Branch Sanitary Sewer Gravity Improvements (NP012400)
Webpage Reviewed: April 6, 2026
HRSD, your regional wastewater treatment utility, is undertaking a project to rehabilitate or replace the sanitary sewer pipeline and manholes along Cedar Lane and Peake Lane. This project will improve performance and reliability within HRSD’s sanitary sewer system.
The rehabilitation portion of work will cover the area on northbound Cedar Lane from the HRSD Cedar Lane Pump Station (PS #104) that is slightly north of West Norfolk Road down to the intersection at Peak Lane and will continue along eastbound Peake Lane to West Norfolk Road. The rehabilitation work will include cured-in-place pipe (CIPP) lining and manhole rehabilitation. CIPP is a jointless, seamless “pipe-within-a-pipe” method that requires little to no digging.
The project also includes the replacement of the sanitary sewer pipeline on northbound Cedar Lane from the intersection of Cedar Lane and Peake Lane to the intersection of Cedar Lane and Greenfield Drive. This section of work for the new sewer pipe will be installed in a trench, meaning pavement cutting and excavation will be necessary to install the new pipe. The new sewer pipe will replace the existing sewer pipe in the same location, and the old pipe will be removed and disposed of. Pavement restoration of the roadways affected by installation of the sewer pipe will occur once the sewer installation is complete.
March 2026 - Notice to Neighbors
April 6, 2026
Construction has not started at this time. The contractor intends to mobilize to the site in May 2026. The contractor will distribute 7-day project notices to the residents prior to beginning work in each area.
Peake Lane Sewer Rehabilitation: Work is expected to begin in May on Peake Lane with CCTV inspections of the sewer pipe, followed by sewer pipe rehabilitation.
Cedar Lane Sewer Improvements: A sewer manhole is planned to be installed in May at the intersection of Cedar Lane and Peake Lane followed by additional sewer pipe installation along Cedar Lane.
Anticipated in May 2026
Spring 2026 - Summer 2027
Immediately following construction when seasonably appropriate
This project is a necessary part of a larger, federally mandated program to reduce sewage overflows during rainstorms. This project will provide updated infrastructure that will help ensure HRSD’s ability to protect public health and the environment for decades to come.
This project includes the rehabilitation and replacement of an existing gravity sewer system.
Disruptions to traffic will be minimized, and in most cases, a single lane of traffic will be maintained. No planned detours are anticipated, but flagging will be used to help direct traffic as needed. All of the project work will be located within the right-of-way. Approximately 3,800 feet of the construction will be “trenchless,” meaning the contractor will not need to dig up the street to fix the pipes. However, approximately 1,725 feet of the sewer pipe and 7 manholes must be replaced by digging
The contractor will ensure that access to residences will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
Work will typically take place Monday through Friday during daylight hours (9 a.m. - 5 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
The work required to rehabilitate the manholes and sewer pipes or replace sanitary sewer pipes should not affect your water or sewer service. If a temporary interruption of service sewer service occurs, the contractor will notify you before work begins so you can plan accordingly. Sewer service typically will be restored within several hours. Your water service should not be affected by this project.
Approximately 1,725 feet of the gravity sewer piping will be replaced by digging. This work will be in the roadway, and pavement restoration of the affected roadways will occur once the sewer installation is complete, when seasonably appropriate.
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, and associated activities should be anticipated.
The contractor has negotiated with a private property owner for a storage area in the project vicinity, and this site will be used for most of the equipment and supplies. The contractor will keep some supplies within the active work zone, in the public right-of way.
Construction workers will not be allowed to park their personal vehicles on the public streets. However, work trucks will be allowed to park within the active work zone.
The estimated cost for the project is approximately $8.8 million and is financed by the wastewater treatment fees paid by HRSD customers.
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the project.
Andre Mendez
RK&K, Newport News, VA
Stephanie Hood
Garney Construction, Virginia Beach, VA
Carter Old
--Milling and Paving Work to Begin--
HRSD, your regional wastewater treatment utility, will begin to mill and pave disturbed sections of pavement along Versailles Avenue, Fontainebleau Crescent, Lasalle Avenue, Tidewater Drive, and Pershing Avenue (please see the map on the back of this notice). This work should take place primarily between the hours of 7 a.m. to 7 p.m., Monday – Friday.
-Temporary Road Closure Notice: Powhatan Avenue at Buckingham Avenue-
HRSD, your regional wastewater treatment utility, is planning a project in your neighborhood to rehabilitate the existing sanitary sewer pipelines and public sewer service connections that are nearing the end of their useful life. This rehabilitation project will increase the systems lifespan while decreasing inflow and infiltration and decreasing risk of failures. The answers to some Frequently Asked Questions (FAQs) are provided here.
--Utility Work to Resume--
HRSD, your regional wastewater treatment utility, will continue work to abandon a sanitary sewer pipeline located along Brick Kiln Boulevard. This work is scheduled to take place Monday through Saturday between the hours of 7 a.m. to 5 p.m.