Construction Notice Update #5 for the City of Norfolk - September 2024

--Milling and Paving to Occur--

 

HRSD, your regional wastewater treatment utility, will begin milling and paving work along Robin Hood Road to restore the roadway surface conditions now that the installation of the new sanitary sewer pipeline is complete.

Read More

Construction Notice Update #3 for the City of Norfolk - September 2024

-- Milling and Paving to Occur --

 

HRSD, your regional wastewater treatment utility, will begin milling and paving work along Chesapeake Boulevard, Cromwell Drive, and Robin Hood Road to restore the roadway surface conditions now that the installation of the new sanitary sewer pipeline is complete

Read More

Construction Notice Update for the City of Norfolk - September 2024

-- Utility Work to Occur --

 

HRSD, your regional wastewater treatment utility, is undertaking a project to inspect and perform maintenance on the sanitary sewer piping along Indian River Road at Poppleton Street. This work should take place primarily between the hours of 8:00 a.m. to 5:00 p.m.

Read More


alertSubscribe

"South Norfolk Sewer Pipe & Manhole Improvements
South Norfolk Area Gravity Sewer Improvements Phase 2

HRSD Capital Improvement Program Project (AT013110)

 

Webpage Reviewed: March 2, 2026
 


HRSD is undertaking a project to rehabilitate and/or replace portions of the sanitary sewer system in the South Norfolk area of Chesapeake and Norfolk. Please see the Roads Affected section of this webpage for specific roads that will be impacted. This effort will improve performance and reliability within HRSD’s sanitary sewer system.

Most of the work will involve Cured-In-Place-Pipe (CIPP) rehabilitation of the existing sewer pipe and manholes. Little to no digging is involved in this process, making it potentially more cost-effective and less disruptive than traditional "dig and replace" pipe repair methods. CIPP is a jointless, seamless, "pipe-within-a-pipe” process. A bypass piping system will be in place to ensure that sewer service is not interrupted.

The remainder of the new sewer pipe and manholes will be installed in a trench, meaning pavement cutting and excavation will be necessary. Pavement restoration of the roadways affected by installation of the sewer pipe will occur once the sewer installation is complete. The existing sewer pipe will not be needed once the new sewer pipe is installed; it will be abandoned in place without disturbing the ground above.

To see which sections of pipe will be rehabilitated and which will be newly installed, please see the maps in the Project map section of this webpage.

What happens during the CIPP process?

The sewer must first be prepared for lining; this includes cleaning the line, removing roots, sediment and grease from the sewer (public and/or private lines) and cutting out intruding connections. The sewer lines and manholes are inspected using closed circuit television (CCTV). Like many types of pipe renewal/replacement, CIPP requires bypass pumping, which re-routes sewer flow around the section of pipe being rehabilitated. This ensures your sewer service is not interrupted. The lining process involves the insertion of a resin-saturated flexible lining into an existing sewer pipe using the manholes located within the street. The lining looks like a very large sock or flexible tube. Either air or water, under pressure, is forced into the tube, which turns the lining inside out and causes it to expand to fit tightly against the existing sewer walls. Hot air or water is circulated throughout the tube to harden the resin. When the curing process is completed (4-8 hours), a new “pipe-within-a-pipe” has been created, eliminating cracks and holes that allow rainwater and roots to enter the sewer and cause operational problems such as stoppages and overflows.

Why is bypass piping and pumping needed?

The sewer system carries wastewater from homes and businesses through pipes to a treatment plant. When sewage pump stations or pipelines require upgrades or replacement, a temporary bypass pumping solution is needed to maintain your sewer service while the existing service is being worked on. These bypass systems ensure that the sewer system remains operational by using a temporary line and pump setup to continue conveying flows away.

How does bypass piping and pumping work?

Because the flow of sewage cannot simply be diverted and service cannot be stopped, it must be “bypassed”—or temporarily pumped around the pipe being repaired or replaced. To do this, pumps capable of pumping all of the wastewater from homes and businesses are brought in, as well as pipes that collects and conveys the flow, on site to continue sewer service.

To see pictures of what the CIPP and bypass system look like, please see the CIPP & Bypass System Fact Sheet.

 

Project Cost: $9.7 Million


Notices

 

December 2025 - Construction Notice #10

November 2025 - Construction Notice #9

October 2025 - Construction Notice #8

October 2025 - Construction Notice #7

October 2025 - Construction Notice #6

October 2025 - Construction Notice #5

September 2025 - Construction Notice #4

July 2025 - Construction Notice #3

May 2025 - Construction Notice #2

April 2025 - Construction Notice #1

February 2025 - Notice to Neighbors

Construction Notice Update #2 for the City of Norfolk - August 2024

--Utility Work, Excavation, and Demolition to Begin--

 

Read More

Construction Notice Update #2 for the City of Norfolk - August 2024

-- Dewatering to Begin and Continued Excavation --

 

HRSD, your regional wastewater treatment utility, in coordination with the City of Norfolk, is planning a project in your neighborhood to replace the existing HRSD City Park Pump Station that is nearing the end of its useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Notice to Neighbors - August 2024

--Norview-Estabrook Neighborhood--

 

Read More

Traffic Advisory - August 5, 2024

NORFOLK – Motorists are advised that HRSD crews will be performing sanitary sewer pipeline improvements at the intersection of Robin Hood Road and Chesapeake Boulevard that requires lane and intersection closures. During this work, traffic will follow a signed detour as indicated on the map below. The detour is scheduled to begin as early as August 6 and is expected to remain in place for 1 to 2 weeks. 

Read More

News Release - July 30, 2024

 

NORFOLK -- HRSD today recognized 108 private and government organizations in Hampton Roads for perfect compliance with their environmental permits during 2023.

Earning Pollution Prevention (P2) awards this year were Department of the Air Force Langley Air Force Base Joint Base Langley-Eustis (greater than 1,000 employees), Canon Environmental Technologies, Incorporated (101—1,000 employees) and Waste Management-Bethel Landfill (less than 100 employees).

Read More

Traffic Advisory - July 26, 2024

NORFOLK – Motorists are advised that HRSD crews will be performing sanitary sewer pipeline improvements at the intersection of Robin Hood Road and Chesapeake Boulevard that requires lane and intersection closures. During this work, traffic will follow a signed detour as indicated on the map below. The detour is scheduled to begin as early as July 29 and is expected to remain in place through late August.

Read More