James River Treatment Plant SWIFT Improvements

Body

--Riverview Farm Park Update--

 

HRSD, your regional wastewater treatment utility, will begin work to install modifications to the area near Riverview Farm Park and the Gymnastics Center. This work should take place primarily between the hours of 7 a.m. to 6 p.m., Monday – Friday.

Construction Update:

  • Construction work to relocate the City’s existing infrastructure and performance of well drilling has been ongoing in the City’s Riverview Farm Park. Well drilling construction hours may vary.
  • In the coming months, work in the park is projected to also include temporary trail paving, completion of the improved access to the gymnastic center and fido field, and the installation of HRSD utilities. 
  • This work will take place during daytime hours and predominately on the City’s property. To maintain safety, access may be temporarily restricted when construction traffic crosses trails.
  • Be aware, during this period of construction. Traffic control measures will be in place.
  • This work should not affect your water or sewer services.
  • This portion of the work is anticipated to be completed by Fall 2023. Due to the nature of construction, work is weather and situation dependent and dates are subject to change.
  • After completion of work for temporary trails and gymnastic center and fido field access, there will be a new location/route for public access to the City’s amenities. 
mapmap

While our project team works diligently to minimize impacts, you may notice increased noise and traffic, along with the people and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site. Due to the nature of construction, work is weather and situation dependent, and dates are subject to change.

More information about this project can be found at the project webpage: www.hrsd.com/james-river-tp-swift-improvements

Thank you for your support of this effort to help achieve HRSD's vision:

Our communities will have clean waterways and reliable water resources for generations to come.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Shawn Maxfield
(757) 833-7483
smaxfield@hrsd.com

HRSD Project Managers:

Efram Fuller
Jennifer Klages
Dan Holloway
Projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Bob Jones
757.833.1742