James River Treatment Plant SWIFT Improvements

Body

--Riverview Farm Park Trails--

 

HRSD, your regional wastewater treatment utility, will be installing under road piping beneath Riverview Parkway that will affect a trail in Riverview Farm Park (please refer to the map below). This work is scheduled to occur from 7:00 am to 5:00 pm (Monday-Friday).

Pipe Installation Operations:

  • Work in Riverview Farm Park will impact the existing trail near one of HRSD’s recharge wells (see map on back of notice) to accommodate pipe installation operations.
  • The Contractor installed a temporary stone trail in preparation of this work for continued usage of the trail system.
  • This work will take place Monday-Friday during the normal work hours.
  • This work should not affect your water or sewer services.
  • This work should take approximately 3-4 weeks. Due to the nature of construction, work is weather and situation dependent and dates are subject to change.
  • The existing trail will be restored upon completion of the work.
  • The work area will be restored as soon as seasonably appropriate.

map

While our project team works diligently to minimize impacts, you may notice increased noise, traffic, crews, and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site.

Please visit the project’s webpage for more information and updates: www.hrsd.com/james-river-tp-swift-improvements.

Thank you for your support of this effort to help achieve HRSD’s vision:

Our communities will have clean waterways and reliable water resources for generations to come.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Shawn Maxfield
757.833.7483
smaxfield@hrsd.com

HRSD Project Manager:

Efram Fuller
Projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Bob Jones
757.833.1742