Hollywood Area Sewer Pipeline & Pump Station Replacement Project

Body

--Sewer Pipe Installation to Begin--

 

HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline in the Cypress Park/Hollywood area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Construction Update:

  • In mid-September, contractors will begin making receiving pits in the Cypress Park area in order to micro tunnel a sewer pipe underground from one pit to another pit.
    • One entrance to Cypress Park will remain open during this work. Portions of the parking lot will be closed off.
    • This work will involve installing sheet piling and excavation.
    • This portion of work is expected to last through early 2026.
  • Additionally, beginning at the end of September, sewer pipe installation will occur on Kentucky Avenue, followed by Hollywood Avenue. This installation will occur with an open-cut trench method, meaning digging will occur from the street to install the pipe underground.
    • Be aware, traffic patterns will include lane closures on Kentucky Avenue and Hollywood Avenue during construction.
    • Access to homes/businesses will be available.
    • This work should not affect your water or sewer services.
    • This portion of the work is anticipated to be completed in 3 to 4 months.
  • Due to the nature of construction, work is weather and situation dependent and dates are subject to change or be extended.

While our project team works diligently to minimize impacts, you may notice increased noise, traffic, crews, and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site.

Please visit the project’s webpage for more information and updates: www.hrsd.com/hollywood-area-sewer-pipeline-pump-station-replacement

Thank you for your support of this effort to help achieve HRSD’s vision:

Our communities will have clean waterways and reliable water resources for generations to come.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Lisa Bolen
757.460.7000
lbolen@hrsd.com

HRSD Project Manager:

Tim Marsh
projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Joeseph Wright
757.382.0109