Robin Hood Road Sewer Replacement

Body

--Nighttime Work to Occur--

 

HRSD, your regional wastewater treatment utility, will begin work to tie-in the new sanitary sewer pipeline along Robin Hood Road into the existing sanitary sewer system. To place the sewer pipe online, wastewater flow in the pipe must be diverted temporarily. Vactor trucks will be used to pump wastewater from one location and haul it to another location. This pump and haul work is expected to occur primarily between the hours of 7pm-8am on the evening of Wednesday June 5th. Night work is necessary for this tie-in as that is when sewage flows in the sewer system are at their lowest.

Construction Update:

  • Beginning the evening of June 5th, nighttime work will occur near the intersection of Robin Hood Road and Birch Street and at the intersection of Robin Hood Road and Kansas Avenue.
  • Be aware, traffic patterns will shift and will include lane closures with flagging. Traffic control measures will be in place.
  • The contractor will ensure that access to residences will be maintained throughout construction.
  • This work should not affect your water or sewer services. Every attempt will be made to provide advance notice of this interruption should it need to occur.
  • This portion of the work is expected to be completed in 24 hours. Due to the nature of construction, work is weather and situation dependent and dates are subject to change.

While our project team works diligently to minimize impacts, you may notice increased noise, traffic, crews, and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site.

Please visit the project’s webpage, www.hrsd.com/robin-hood-road-sewer-replacement for more information and updates.

Thank you for your support of this effort to help achieve HRSD's vision:

Our communities will have clean waterways and reliable water resources for generations to come.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Lisa Bolen
(757) 460-7000
lbolen@hrsd.com

HRSD Project Manager:

Tim Marsh
Projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Andre Mendez