Luxembourg and Ashland Circle Pump Station Replacements
--Versailles Avenue Work and No Street Parking to Begin--
HRSD, your regional wastewater treatment utility, in coordination with the City of Norfolk, is conducting a project in your neighborhood to replace the existing HRSD Luxembourg and Ashland Circle Pump Stations that are nearing the end of their useful life. This replacement project will also improve the sewer system’s performance and ensure continued, reliable sewer service in the future. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.
Construction Update:
- Beginning as early as January 10th, installation of the dewatering system along Versailles Avenue will occur in the vicinity of your home/business on Versailles Avenue between Luxembourg Street and Norway Place.
- This work will take place during the daytime and within the right-of-way. Nighttime work is not anticipated, but if it needs to occur, the contractor will notify you in advance.
- Be aware, traffic patterns will shift and will include partial lane closures and detours to through traffic during the dewatering system installation.
- Residents will have access to driveways, but street parking will not be available during the dewatering installation.
- This work should not affect your water or sewer services.
- This portion of the work is anticipated to be completed in 3 to 4 weeks. Due to the nature of construction, work is weather and situation dependent and dates are subject to change or be extended.
For more information, please visit the project’s webpage: Luxembourg and Ashland Circle Pump Station Replacements | HRSD.com
Thank you for your support of this effort to help achieve HRSD's vision:
Our communities will have clean waterways and reliable water resources for generations to come.
Should you have any questions or comments, you may contact:
Lisa Bolen
(757) 460-7000
LBolen@hrsd.com
Phil Hubbard
projects@hrsd.com
Bob Doyle
(757) 382-0109