Bolling Avenue Sanitary Sewer Replacement
HRSD, your regional wastewater treatment utility, in coordination with the City of Norfolk, is planning a project in your neighborhood to replace the existing HRSD and City sanitary sewer pipelines and public sewer service connections that are nearing the end of their useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.
Project Overview
The project is located along Bolling Avenue between Studeley Avenue and Powhatan Avenue. This project includes improving pipelines, manholes, and sewer service lateral pipes. Theses pipes will be repaired or replaced within the city right-of-way. The owner of any private sewer service pipe that is found in need of repair, will be contacted. The contractor will maintain a clean job site and minimize traffic disruption.
Project Schedule
Pre-Construction:
December 2024 - January 2025
Condition Assessment photos and videos of exterior components of adjacent properties taken from the public right-of-way.
Installation of a vibration and groundwater monitoring system adjacent to the work area.
Construction:
Mid-January 2025 - Early May 2025
Installation of sewer pipelines and service laterals along Bolling Avenue.
Restoration:
Immediately following construction when seasonably appropriate.
Thank you for your support of this effort to help achieve HRSD's vision: Our communities will have clean waterways and reliable water resources for generations to come.
Should you have any questions or comments, you may contact:
Lisa Bolen
757.460.7000
LBolen@hrsd.com.