Lee Avenue & Wesley Street Sewer Valve Replacement

Body

 

HRSD, your regional wastewater treatment utility, is planning a project in your area to replace an existing sewer pipe valve nearing the end of its useful life. This valve replacement project will improve the sewer system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.

Project Overview
HRSD is undertaking a project to replace a sewer valve with a new 42-inch valve along the existing sanitary sewer pipeline at the intersection of Wesley Street and Lee Avenue. The piping and valves will be installed in a trench, meaning pavement cutting and excavation will be necessary. Pavement restoration of the roadways affected by installation of the valves will occur once installation is complete.

Bolling Avenue

 

Project Schedule
Staging:
Early 2025

Construction:
Early 2025 - Spring 2025

Restoration:
Immediately following construction when seasonably appropriate.

Thank you for your support of this effort to help achieve HRSD's vision: Our communities will have clean waterways and reliable water resources for generations to come.

 

 

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist

Lisa Bolen
757.460.7000
LBolen@hrsd.com.