Gravity Sanitary Sewer Improvements: Seay Avenue Update

Body

 

HRSD, your regional wastewater treatment utility, in coordination with the City of Norfolk, will soon begin a project in your neighborhood to rehabilitate existing HRSD sanitary sewer pipelines that are nearing the end of their useful life. This rehabilitation project will ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) can be found here.

Project Overview

This project is in the vicinity of the 3500 block of Seay Avenue in Norfolk, Virginia. The project includes the repair of existing sanitary sewer pipelines and manholes to like-new condition. As part of the work, pipelines will undergo heavy cleaning and interior lining, new manhole frames and covers will be installed, and the manhole interiors will be lined. Work may begin as early as March 10.

Temporary sanitary sewer bypass pumping will be required to complete the work. This will ensure that your sewer service is not interrupted. All work will be within the city right-of-way or on HRSD property. The contractor will maintain a clean job site.

map

Project Schedule

Staging: March 2025

Construction: March 2025 - May 2025

Restoration: Immediately following construction. All restoration is on HRSD property and outside of the city right-of-way.

 

 

 

 

 

 

 

Thank you for your support of this effort to help achieve HRSD's vision:

Our communities will have clean waterways and reliable water resources for generations to come. 

 