South Norfolk Pump Stations & Sanitary Sewer Replacement Project

Body

--Project Update--

 

Rodgers Street Sewer Pipeline Update


imageOur contractors have begun excavation on Rodgers Street and are scheduled to begin installation of new sewer pipeline in the second half of June. This pipeline work is expected to reach Holly Avenue by the beginning of July.

During excavation and the installation of pipeline, Rodgers Street will be restricted with no through driving allowed between Park Avenue and Byrd Avenue to ensure safety around the construction area. However, although barriers will be in place, residents will be able to access their homes via the side street of Holly Avenue and various alleys. The pipeline work on Rodgers Street is expected to be completed by early 2025.

While the contractors work on Rodgers Street, you may hear noises such as engines, backup alarms, diesel generators and motors. Vibration monitors will be located onsite and near the construction area to ensure limited disruption to you in your residence. Your water and sewer service will not be disrupted. Dust control measures such as paving, frequent road cleaning and/or application of water will be enacted to reduce dust from becoming airborne. After construction, roadways and rights-of-way will be restored to their pre-construction structure and materials.

 

Park Avenue Pump Station Update

imageConstruction continued at the Park Avenue pump station this month, concentrating on the installation of a manhole in front of the pump station site to allow access to the line flowing into the station. The contractors also backfilled the soil around the exterior walls of the station and created openings in the top slab to allow for the eventual installation of wiring.

Continuing construction work will occur directly on the pump station property itself, Monday – Friday between the hours of 7 AM – 6 PM. As a reminder, construction of this pump station is ongoing until summer 2025.

 

Park Avenue Pipeline Work Update

Our contractors are working on installing the last runs of storm drain pipe and water line at the intersection of Stewart Street and Park Avenue. During late June and early July, our contractors are tentatively scheduled for restoration work on Park Avenue including repairing the roadway, reconstructing gutters, rebuilding curbs, laying down an asphalt base on the road, repouring the sidewalk, reseeding excavated soul, and performing a surface paving.

Park Avenue will continue to be restricted with no through driving allowed between Hull Street and Jackson Avenue to ensure safety around the construction area. Work on Park Avenue between Bainbridge Boulevard and Hull Street has been extended, and the road is currently restricted until late 2024 at the earliest. However, although barriers will be in place, residents will be able to access their homes and alleys via Stewart Street, Decatur Street, and Rodgers Street between Jefferson Street and Holly Avenue. The pipeline work on Park Avenue is expected to be completed by late 2024.

 

Ferebee Pump Station Update

The replacement structure for Ferebee Pump Station is in its final design stages and is expected to begin construction during late 2024.

While our project team works diligently to minimize impacts, you may notice increased noise and traffic, along with the people and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site. Due to the nature of construction, work is weather and situation dependent, and dates are subject to change.

More information about this project can be found at the project webpage:
www.hrsd.com/south-norfolk-pump-stations-and-sanitary-sewer-replacement-project

 

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Lisa Bolen
757.460.7000
lbolen@hrsd.com

HRSD Project Manager:

Nick Taschner
projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Michael Hughs
757.692.5128