-
Subscribe
-
"South Norfolk Pump Stations and Sanitary Sewer Replacement Project"
Ferebee Avenue Pump Station Replacement
Sanitary Sewer Project 1950 - Part 1
Sanitary Sewer Project 1950 - Part 2
Park Avenue Pump Station ReplacementHRSD Capital Improvement Program Project (VP014010, VP014021, VP014022 & VP018000)
-
In Summer 2022, HRSD began a multi-year project to replace critical aging infrastructure in the South Norfolk community. This project consists of three phases that will replace two aging sanitary sewer pump stations and their associated sanitary sewer pipes. To improve sewer system reliability and provide for future capacity, the pump stations will be demolished and rebuilt on adjacent lots. The pipelines between these two pump stations are being replaced and, in certain cases, rehabilitated. For the pump station and sewer pipe locations, please refer to the Project Map.
- Park Avenue Pump Station: The current pump station is located at 503 Park Avenue. Once the new pump station is built on the corner of Park Avenue and Porter Street, the former pump station will be demolished. For artist renderings on what the new pump station will look like, please view the presentation in the Online Meetings & Events section of this webpage.
- Sanitary Sewer Pipeline Replacement: The pipelines that will connect to the two pump stations will be replaced or rehabilitated. This work will occur along Park Avenue, Rodgers Street, Byrd Avenue, and Bainbridge Boulevard.
- Ferebee Avenue Pump Station: The current pump station is located across from Ferebee Avenue at 2812 Bainbridge Boulevard. Once the pump station is built on the adjacent lot at 2900 Bainbridge Boulevard, the former pump station will be demolished. For artist renderings on what the new pump station will look like, please view the presentation in the Online Meetings & Events section of this webpage.
Project Cost: Approximately $35,800,000
-
Notices
October 2025 - Construction Notice Update #66
October 2025 - Construction Notice Update #65
September 2025 - Construction Notice Update #64
September 2025 - Construction Notice Update #63
August 2025 - Construction Notice Update #62
August 2025 - Construction Notice Update #61
July 2025 - Construction Notice Update #60
July 2025 - Construction Notice Update #59
June 2025 - Construction Notice Update #58
June 2025 - Construction Notice Update #57
May 2025 - Construction Notice Update #56
April 2025 - Construction Notice Update #55
March 2025 - Construction Notice Update #54
March 2025 - Construction Notice Update #53
March 2025 - Construction Notice Update #52
February 2025 - Construction Notice Update #51
January 2025 - Construction Notice Update #50
-
November 5, 2025
Dust control measures such as paving, frequent road cleaning and/or application of water will be enacted to reduce dust from becoming airborne in our construction areas. After construction, roadways and rights-of-way will be restored to their pre-construction structure and materials.
Bainbridge Boulevard Pipeline Work Update: In October, excavation and pipeline work continued at the intersection of Swain Avenue and Bainbridge Boulevard with the installation and cleaning out of manholes along with pressure testing. Restoration of this area is underway with the forming and pouring of concrete curbs, gutters, handicap ramps, and driveway aprons. Contractors also prepared the area for temporary asphalt paving.
Our team mobilized to the intersection of Bainbridge Boulevard and Byrd Avenue and began excavation and installation of pipe towards Orville Avenue. During this period, the intersection is currently closed to traffic due to excavation. Residents on Byrd Avenue are instructed to access their street using a detour via Wilbur Avenue from Bainbridge Boulevard and then taking Chamberlain Avenue to Byrd Avenue. This is expected to continue through November.
The pipeline construction is planned to be completed by late 2025.
Ferebee Avenue Pump Station Update:After the installation of rebar and reinforcing steel to provide fortification within concrete forms, several concrete pours were carried out in late September and October to form the Ferebee Avenue Pump Station’s foundation slab and wet well walls.
During material deliveries, soil/debris removal, or concrete pours, southbound traffic on Bainbridge Boulevard may be reduced to one lane for the safety of our contractor crews and customers.
Final pump station construction is expected to be completed by late 2027.
Park Avenue Pump Station Construction Update:Start-up preparation activities have continued at the Park Avenue Pump Station including the installation and testing of generator elements, testing of valves and pumps, and further calibration of flow meters.
Construction at the pump station site is ongoing through the end of 2025.
Perry Street Pipeline Update:The sewer pipe installation is complete at the intersection of Perry Street and Park Avenue.
Further sewer pipeline installation southward on Perry Street is expected to take place during summer 2026.
-
All work will be confined to HRSD property and road rights-of-way.
Impacted roads will include:
- Park Avenue
- Rodgers Street
- Byrd Avenue
- Bainbridge Boulevard
-
- Design:
-
Ongoing through Fall 2024
- Park Avenue Pump Station Construction:
-
Fall 2022 - Late 2025
- Sanitary Sewer Pipeline Construction:
-
Summer 2022 – Late 2026
- Ferebee Pump Station Construction:
-
Early 2025 – Late 2027
-
-
The project is necessary in order to provide reliable conveyance of sewage in the South Norfolk area. Replacing the existing pump stations with new modernized infrastructure will help to ensure wastewater capacity is adequate and will optimize HRSD’s ability to protect public health and the environment for decades to come.
-
No. Although this program includes designing new pump stations and sewer lines that can withstand flooding from major storm events, it is not intended to collect or eliminate storm water. The new pump stations and sanitary sewer lines will have increased capacity which will minimize sanitary sewer overflows (SSOs), but the system is not designed to be a stormwater collection and treatment system.
-
During the design phase of this project (ongoing through Spring 2024), surveyors or contractors may be seen working in the area. All survey work during this time will be completed in public rights-of-way. If access to a private property is needed, permission will be secured in advance with the property owner.
-
Disruptions to traffic will be minimized, and, in most cases, a single lane of traffic will be maintained. Some road closures will be necessary, and detours will be in place. Access to homes/businesses will be available.
-
The contractor will ensure that access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
To protect residential structures during construction, over 35 vibration monitoring locations will be installed for use throughout the installation of sanitary sewer lines. Vibration monitoring will be carried out in advance of and during construction. Alerts are provided to contractor if the vibrations reach a particular level and work will be stopped if these vibrations exceed federally-established levels that may cause damage to residential structures.
-
For the sanitary sewer pipeline work occurring on Park Avenue, construction may occur Monday through Saturday between the hours of 7 a.m. and 7 p.m. However, for the other phases of the project, work will typically take place Monday through Friday during daylight hours (8 a.m. - 4 p.m.). There may be times when extended hours, work at night, or weekend work is necessary, but changes in work hours will be announced ahead of time to impacted individuals.
-
Your sewer service will be temporarily interrupted if work is to be performed on the sewer lateral pipe that serves your property. The contractor will notify you before your lateral is to be rehabilitated so you can plan appropriately. Sewer service typically will be restored within several hours. Your water service should not be affected by this program.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the program.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, etc. should be anticipated during daylight hours (8 a.m. - 4 p.m.). If night work is to occur, affected residents will receive a notification ahead of the work.
-
An off-site storage area in the program vicinity will be used for the storage of most of the equipment and supplies. Some supplies may be contained within the active work zone, in the public right-of way.
-
Construction workers will not be allowed to park their personal vehicles on the public streets. However, work trucks will be allowed to park within the active work zone.
-
The estimated cost for the program is $35.8 million and is financed by the wastewater and wastewater treatment fees paid by HRSD customers.
-
The project website will be updated on a monthly basis regarding any schedule changes or project updates and can be accessed at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
- Public Inquiries
-
Lisa Bolen
757.460.7000 (Office)
- Project Manager
- Nick Taschner
- Additional Information
-
Projects@hrsd.com
-
- Chief of Communications
-
Leila Rice, APR
757.460.7056 (Office)
-
- Engineering Consultant Firm:
-
Gannett Fleming, Virginia Beach, VA
- Contractor:
-
Bridgeman Civil (Sewer Pipe Installation)
- Contractor:
-
Shaw Construction (Park Avenue Pump Station)
Shaw Project Manager: Chuck Thompson
- Contractor:
-
ACE Service Inc. (Ferebee Pump Station)