South Norfolk Pump Stations & Sanitary Sewer Replacement Project
--Project Update--
Bainbridge Boulevard Sewer Pipeline Update
Construction continues at the intersection of Swain Avenue and Bainbridge Boulevard with the excavation and installation of new pipe and manholes.
While construction is underway, access to Swain Avenue at this intersection is closed. Residents may access Swain Avenue by turning into the loop at Southgate Plaza as show in the map to the right and then onto Swain Avenue. Access back to Bainbridge Boulevard from Swain Avenue is available via the route shown in blue.
The pipeline construction is planned to be completed by late fall 2025.
Ferebee Avenue Pump Station Update
Excavation has begun at the Ferebee Avenue Pump Station site, which will be followed by installation of concrete formwork and rebar in preparation for pouring the foundation. A dewatering system has been installed to ensure a dry, stable work area.
During material deliveries, soil/debris removal, or concrete pours, southbound traffic on Bainbridge Boulevard may be reduced to one lane for the safety of our contractor crews and customers.
Final pump station construction is expected to be completed by late 2027.
Park Avenue Pump Station Update
Construction continues at the pump station to prepare for start-up, including the installation of generator components, calibration of flow meters, and the testing of pumps. Construction is ongoing through late 2025.
While our project team works diligently to minimize impacts, you may notice increased noise and traffic, along with the people and heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site. Due to the nature of construction, work is weather and situation dependent, and dates are subject to change.
More information about this project can be found at the project webpage:
www.hrsd.com/south-norfolk-pump-stations-and-sanitary-sewer-replacement-project
Should you have any questions or comments, you may contact:
Lisa Bolen
757.460.7000
lbolen@hrsd.com