South Norfolk Pump Stations & Sanitary Sewer Replacement Project
--Ferebee Pump Station Construction Update--
Ferebee Pump Station Top Slab Pour

During the week of January 13, our contractors will have a concrete pour for one day at the new Ferebee Pump station site to form the top slab of the new pump station.
On the pour day, one to three concrete pump trucks will be staged on Ferebee Avenue across from the pump station site, seen in green to the right. Additional trucks may be staged on Edgewood Avenue, seen in the blue area to the right.
Setup will begin at 6:00 a.m., and the pour will begin at 7:00 a.m. Contractor staff or “flaggers”, stationed in the orange areas on the map, will be present to guide traffic coming in and out of Ferebee and Edgewood Avenues and around trucks stationed on Bainbridge Boulevard as the pour happens. Our contractors may request a lane shutdown with the city to stage the trucks in front of the work site. Work is anticipated to be completed by the end of the day.
Final pump station construction is expected to be completed in late 2027.
Bainbridge Boulevard Sewer Pipeline Update
Sewer pipe installation is currently occurring on Bainbridge Boulevard between Wilbur Avenue and Orville Avenue, starting with the intersection at Wilbur Avenue and moving south toward Swain Avenue.
During pipeline construction, Bainbridge Boulevard will be closed in the northbound lane around the construction areas near Wilbur Avenue. Residents on Wilbur Avenue can access their homes via local traffic routes (per the map in Construction Notice #67).
The pipeline construction is planned to be completed by summer 2027.
Park Avenue Pump Station Update
Start-up preparation activities have continued at the Park Avenue Pump Station, including site grading along with excavation and placing of stone base for the station driveway. Construction is ongoing through spring 2026.
More information about this project can be found at the project webpage:
www.hrsd.com/south-norfolk-pump-stations-and-sanitary-sewer-replacement-project
Should you have any questions or comments, you may contact:
Lisa Bolen
757.460.7000
lbolen@hrsd.com
Nick Taschner
projects@hrsd.com
Michael Hughs
757.692.5128