South Norfolk Pump Stations & Sanitary Sewer Replacement Project

Body

--Project Update--

 

Park Avenue and Perry Street Sewer Pipeline Work Update

construction imageSewer pipeline replacement work on Perry Street resumed in mid-June with excavation and the installation of a manhole at the intersection of Park Avenue and Perry Street.

Following the installation of this manhole, contractors will conduct excavation and sewer pipe replacement in the area starting at Park Avenue and working towards the southern end of Perry Street.

 

Due to this construction, Perry Street will be closed to through traffic with no street parking. Work is expected to be completed by the end of September 2026.

 

 

During the work period, these conditions will be in place: project map

  • Access for residents on Perry Street shall be maintained at all times. Occasionally, driveway access may be impacted, but we will work with residents to address any concerns. Residences can be accessed from both Park Avenue and by the yellow access route depicted in the map to the right.
  • Mail and package service delivery to residents will not be impacted, and contractors will work with delivery services to ensure that mail and packages reach your home.
  • Trash service will continue to be picked up in the locations where you typically place your trash.

 

 

 

 

 

 

 

 

 

construction photoFerebee Avenue Pump Station Update

Construction continues at the Ferebee Pump Station site at 2812 Bainbridge Boulevard with the installation of trusses for the station roof, pipe support stanchions, header pipes, and suction line. Welding of beams has taken place to support the station’s stairwell.


During material deliveries, soil/debris removal, or concrete pours at the pump station site, southbound traffic on Bainbridge Boulevard may be reduced to one lane for the safety of our contractor crews and customers.


Final pump station construction is expected to be completed by late 2027.

 

 

 

 

 

Bainbridge Boulevard Sewer Pipeline Work Update

Bainbridge Boulevard’s intersection with Chesapeake Drive remains open to local/thru traffic due to adjustments in the work schedule. Notice will be provided when work in this area resumes. construction photo


Restoration work has occurred on Bainbridge Boulevard between Post Avenue and Wright Avenue, consisting of reconstruction of the curb along with installation of temporary asphalt.


The overall project pipeline construction is expected to be completed by summer 2027.

 

 

 

 

While our project team works diligently to minimize impacts, you may notice increased traffic and noise such as drilling, engines, backup alarms, diesel generators and motors, along with the people and heavy equipment associated with construction. Please proceed with caution when traveling around the construction area and for your safety, do not enter the work zone.

  • Vibration monitors are in place to ensure that vibration levels are kept below the allowed threshold.
  • Your water and sewer service will not be disrupted.
  • Due to the nature of construction, work is weather and situation dependent, and dates are subject to change

For more information about this project, visit:
www.hrsd.com/south-norfolk-pump-stations-and-sanitary-sewer-replacement-project

 

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Lisa Bolen
757.460.7000
lbolen@hrsd.com

HRSD Project Manager:

Nick Taschner
projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Michael Hughs
757.692.5128