Lucas Creek Pump Station Replacement

Body

--Early Morning Concrete Pour--

 

HRSD, your regional wastewater treatment utility, will begin work to pour concrete for the new Pump Station building. Due to the extended amount of time, it will take to pour a large quantity of concrete, we are planning to start earlier in the morning outside of normal work hours. This early morning work should take place primarily between the hours of 4 a.m. to 6 p.m., Monday – Friday.

Construction Update:

  • Beginning as early as September 26, an early concrete pour will begin in the vicinity of your home/business.
  • This work will take place during the daytime on the project site.
  • This work should not affect your water or sewer services.
  • This portion of the work should take approximately one to three days.  
  • Due to the nature of construction, work is weather and situation dependent and dates are subject to change.

While our project team works diligently to minimize impacts, you may notice increased noise, traffic, and the use of heavy equipment (with back-up safety alarms) associated with construction. Please take care when traveling around the construction area and for your safety, do not enter the site.

For more information, please visit the project’s webpage: Lucas Creek Pump Station Replacement | HRSD.com

 

Thank you for your support of this effort to help achieve HRSD's vision:

Our communities will have clean waterways and reliable water resources for generations to come.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Shawn Maxfield
(757) 833-7483
smaxfield@hrsd.com

HRSD Project Manager:

Ted Denny
projects@hrsd.com

Onsite Inspector (Emergent Concerns):

Nelson Da Cruz
(757) 652-1914