Gravity Sewer Improvements

Body

 

HRSD, your regional wastewater treatment utility, in coordination with the City of Hampton, is planning a project in your neighborhood to rehabilitate the existing HRSD sewer pipelines and manholes that are nearing the end of their useful life. This rehabilitation project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.

Project Overview
The project is in the neighborhood surrounding Seaboard Avenue from the Mallory Street intersection to the Buckroe Avenue Intersection and in the neighborhood along Bay Shore Lane, South 1st Street and Seaboard Avenue. This project includes pipelines and manholes. These pipes and select manholes will be repaired within the HRSD easement. The owner of any private sewer service pipe that is found in need of repair will be contacted. The contractor will maintain a clean job site and minimize traffic disruption.

map map

Project Schedule
Staging: July 2023
Construction: July 2023 - Spring 2024
Restoration: Immediately following construction when seasonably appropriate

You may also visit www.hrsd.com/gravity-sewer-improvements for additional information and project updates.

If you have any questions, concerns, or comments about the project, please feel free to contact Shawn Maxfield, HRSD North Shore Public Information Specialist, at 757.833.7483 or smaxfield@hrsd.com.

Thank you for your support of this effort to help achieve HRSD's vision: Our communities will have clean waterways and reliable water resources for generations to come.