Lasalle Avenue Sewer Replacement

Body

 

HRSD, your regional wastewater treatment utility, is planning a project in your neighborhood to replace the existing HRSD sanitary sewer pipelines that are nearing the end of their useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.

Project Overview

HRSD is undertaking a project to replace the sanitary sewer pipeline along Versailles Avenue, Lafayette Boulevard, Fontainebleau Crescent, Lasalle Avenue, Tidewater Drive, and Pershing Avenue. This effort will improve performance and reliability within HRSD’s sanitary sewer system. The new sewer pipe will be installed in a trench, meaning pavement cutting and excavation will be necessary to install the new pipe. Pavement restoration of the roadways affected by installation of the sewer pipe will occur once the sewer installation is complete. The existing sewer pipe will not be needed once the new sewer pipe is installed; it will be abandoned in place without disturbing the ground above.

map

Project Schedule
Staging: March 2024
Construction: April 2024 – Early 2025
Restoration: Immediately following construction when seasonably appropriate

If you have any questions, concerns, or comments about the project, please feel free to contact Lisa Bolen, HRSD Public Information Specialist, at 757.460.7000 or LBolen@hrsd.com.

You also may visit www.hrsd.com/lasalle-avenue-sewer-replacement for additional information and project updates.

Thank you for your support of this effort to help achieve HRSD’s vision: Our communities will have clean waterways and reliable water resources for generations to come.