-
Subscribe
-
"Lasalle Avenue Sewer Replacement"
Norview Estabrook Division I 18-inch Force Main Replacement Phase III
HRSD Capital Improvement Program Projects (VP016700) -
HRSD is undertaking a project to replace the sanitary sewer pipeline along Versailles Avenue, Lafayette Boulevard, Fontainebleau Crescent, Lasalle Avenue, Tidewater Drive, and Pershing Avenue. This effort will improve performance and reliability within HRSD’s sanitary sewer system. The new sewer pipe will be installed in a trench, meaning pavement cutting and excavation will be necessary to install the new pipe. Pavement restoration of the roadways affected by installation of the sewer pipe will occur once the sewer installation is complete. The existing sewer pipe will not be needed once the new sewer pipe is installed; it will be abandoned in place without disturbing the ground above.
Project Cost: approximately $4 million
-
Notices
July 2024 - Construction Notice Update #3
June 2024 - Construction Notice Update #2
May 2024 - Construction Notice Update #1
March 2024 - Notice to Neighbors
-
April 30, 2025
Sanitary sewer pipeline installation along Tidewater Drive was completed in August. The remaining installation of sewer pipe on Lasalle Avenue, Fontainebleau Crescent, Lafayette Boulevard, and Versailles Avenue is being scheduled. An update will be posted when that information is known.
-
The work will be confined to the following areas:
- The intersection of Versailles Avenue and Lafayette Boulevard
- Fontainebleau Crescent between Lafayette Boulevard and Lasalle Avenue
- Lasalle Avenue between Fontainebleau Crescent and Tidewater Drive
- Tidewater Drive between Lasalle Avenue and Pershing Avenue
- The intersection of Pershing Avenue and Tidewater Drive
Comprehensive traffic control plans will be implemented to minimize inconvenience.
-
- Staging:
-
Spring 2024
- Construction:
-
Spring 2024 – Summer 2025
- Restoration:
-
Immediately following construction when seasonably appropriate
-
-
This project is a necessary to upgrade aging infrastructure that will help ensure HRSD’s ability to protect public health and the environment for decades to come.
-
We look at several routes/sites to determine what meets HRSD’s needs of availability, price, location, property agreement terms, and ease of access to the sewer pipe for construction and future maintenance.
-
Disruptions to traffic will be minimized. Detours and lane closures with flaggers will be used to help direct traffic as needed.
-
The contractor will ensure access to residences will be maintained throughout construction. Trash and mail services should not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
Work will typically take place Monday through Friday from 7 AM - 7 PM; there may be exceptions in certain locations to reduce impacts to the community, adhere to City ordinances, or as required in order to complete the work.
-
Your water and sewer service may be briefly affected by this project. Every attempt will be made to provide an advance notice of this interruption if it is to occur so you can plan accordingly.
-
Where sewer pipeline is installed, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, materials being delivered, diesel generators, air compressors, sawing, and associated activities should be anticipated.
-
The contractor has negotiated with a private property owner for a storage area in the project vicinity, and this site will be used for most of the equipment and supplies. The contractor will keep some supplies within the active work zone, in the public right-of way.
-
Construction workers will not be allowed to park their personal vehicles on the public streets. However, work trucks will be allowed to park within the active work zone.
-
The estimated cost for the project is approximately $4 million and is financed by the wastewater treatment fees paid by HRSD customers.
-
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the project.
-
- Public Information Specialist:
-
Lisa Bolen
757.460.7000 (Office)
- HRSD Project Manager:
- Phil Hubbard
- Additional Information:
- Projects@hrsd.com
-
- Director of Communications:
-
Leila Rice, APR
757.460.7056 (Office)
-
- Onsite Inspector (immediate/emergent concerns):
-
Andre Mendez
- Engineering Consultant Firm:
-
RK&K, Virginia Beach, VA
- Engineering Consultant Project Lead:
-
Ryan Delo
- Contractor:
-
Bridgeman Civil Inc., Suffolk, VA
- Contractor Field Project Manager:
-
Taylor Bridgeman