Sewer Manhole Rehabilitation Project

Body

 

HRSD, your regional wastewater treatment utility, is undertaking a project to rehabilitate and perform
maintenance for an existing sanitary sewer manhole located at 114 Normandy Lane in Newport News,
Virginia. In order to achieve the rehabilitation needed for the manhole, the contractor will need to use
bypass pumps to move the sewer flow through a temporary bypass pipe. These bypass pumps will be
installed in the manhole in front of 112 Normandy Lane, and bypass piping will be placed in the right-of-
way off the side of the road to the pump station located at 114 Normandy Lane. The bypass piping will
either be buried or a flow ramp will be used in front of driveways to keep access to the home at 112
Normandy Lane. Temporary lane closures may be needed it install the bypass piping for a short
duration. The answers to some Frequently Asked Questions (FAQs) are provided here.

Image

Project Schedule

  • Work should begin the week of December 13th
  • Bypass pumps should only run for a duration of one week during the work
  • Restoration of the area should occur in December

Thank you for your support of this effort to help achieve HRSD's vision: Future generations will inherit clean waterways and be able to keep them clean.

Should you have any questions or comments, you may contact:

HRSD Public Information Specialist:

Lisa Bolen
(757) 460-7000
lbolen@hrsd.com

HRSD Project Manager:

Philip Hughes
(757) 833-7426