Construction Notice Update #16 for the City of Hampton - March 2025

--Pavement Restoration Work to Occur--

HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. The areas around the completed manholes will be restored. The restoration work will include milling and paving. The work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday, and could include weekend work.

Read More

Construction Notice Update #15 for the City of Hampton - December 2024

--Utility Work to Occur--

Read More

Construction Notice Update #5 for the City of Hampton - November 2024

--Utility Work to Begin--

HRSD, your regional wastewater treatment utility, will continue the sanitary sewer rehabilitation work along Fox Hill Road and Beach Road from Old Buckroe Road to Westlawn Drive. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Construction Notice Update #4 for the City of Hampton - November 2024

--Utility Work to Begin--

HRSD, your regional wastewater treatment utility, will continue the sanitary sewer rehabilitation work along Lemaster Avenue from Fox Hill Road to Fort Worth Street, down Fort Worth Street to Harris Creek Road, and continuing down Harris Creek Road to East Little Back River Road. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Construction Notice Update #14 for the City of Hampton - October 2024

--Utility Work to Occur--

HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday, but could include weekend work.

Read More

Construction Notice Update #13 for the City of Hampton - September 2024

--Utility Work to Occur--

HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday, but could include weekend work.

Read More

Construction Notice Update #3 for the City of Hampton - September 2024

--Utility Work to Begin--

HRSD, your regional wastewater treatment utility, will begin the sanitary sewer rehabilitation work along Lemaster Avenue from Fox Hill Road to Fort Worth Street, down Fort Worth Street to Harris Creek Road, and continuing down Harris Creek Road to East Little Back River Road. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Traffic Advisory - September 6, 2024

HAMPTON – Motorists are advised that HRSD crews will continue to perform sanitary sewer pipeline improvements at E. Mellen Street and N. Willard Avenue that require a closure between E. Howard Street and E. Mercury Boulevard. During this work traffic will follow a signed detour using E. Howard Street, N. Curry Street, and E. Mercury Boulevard as indicated on the map below. Motorists can use E. Mercury Boulevard to gain access to Fort Monroe. Local traffic will continue to have access to homes and businesses within the closed section of E.

Read More

Construction Notice Update #12 for the City of Hampton - August 2024

--Utility Work to Occur--

HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work includes the replacement of the water line near E. Cummings Avenue and N. Willard Avenue. The water line replacement work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday, but could include weekend work.

Read More

Notice to Neighbors - August 2024

-- Work to occur from the National Avenue and Willard Avenue intersection to Downes Street --

HRSD, your regional wastewater treatment utility, is working to repair a line break that was discovered on Tuesday, August 6, near Hampton University. To prevent any sanitary sewer spills, crews will install a bypass sewer pipeline from the Willard Avenue Pump Station located at the corner of National Avenue and S. Willard Avenue to Downes Street.

Read More