HRSD, your regional wastewater treatment utility, is undertaking a project to replace the existing Willard Avenue Pump Station located at 219 National Avenue and associated gravity sewer lines. The new pump station, located at the corner of S. Willard Avenue and Downes Street, will resolve capacity, operational, and maintenance issues that currently affect the existing pump station as it nears the end of its useful life. The new gravity sewer on Willard Avenue from National Avenue to Downes Street will be replaced to redirect flow and resolve Infiltration and Inflow issues. When the new pump station is completed, the existing pump station will be removed, and the existing site will be returned to green space. Additional gravity sewer work will be completed along Willard Avenue between Downes Street and E. Kelly Avenue to resolve similar infiltration and Inflow issues.
To view the map of the Willard Avenue Pump Stations, click here.
Project Cost: $16,000,000
-
Notices
March 2025 - Construction Status Update #17
March 2025 - Construction Status Update #16
December 2024 - Construction Status Update #15
October 2024 - Construction Status Update #14
September 2024 - Construction Status Update #13
-
April 30, 2025
The pump station and associated generator and odor control building construction is nearing completion and is expected to be operational by Spring of 2025. Upon completion of the pump station, the associated sewer pipe work will occur from National Avenue to Downes Street which is expected to be complete by Summer 2025.
Restoration of Willard Avenue east of Downes Street will begin in March 2025. This work is expected to continue through Spring 2025. Traffic control, and bypass piping will remain in place for the duration of the work and some detours and road closures may be required. Access and parking for residents and businesses will be maintained.
Weekend Work to Occur: The contractors are scheduled to do some electrical and general construction activities at the pump station site at the corner of S. Willard Avenue and Downes Street on Saturday, April 26, between the hours of 8:00 a.m. – 5:00 p.m.
-
The majority of the work regarding the pump station will be conducted on HRSD property and will have minimal impact on traffic; however, construction traffic will be entering and exiting the site from S. Willard Avenue and Downes Street. The gravity sewer work planned for S. Willard Avenue will require isolated lane closures. Comprehensive traffic control plans will be implemented to minimize inconvenience.
-
- Staging:
-
Fall 2022
- Construction:
-
Fall 2022 - Summer 2025
- Restoration:
-
Immediately following construction when seasonably appropriate
-
-
The project is necessary in order to provide reliable conveyance of sewage in the Phoebus area. Replacing the existing pump station with new modernized infrastructure will help to ensure wastewater capacity is adequate and will optimize HRSD’s ability to protect public health and the environment for decades to come.
-
The project consists of work to be done on HRSD property as well as sewer pipeline work to be installed in S. Willard Avenue and Downes Street. The majority of this work will be conducted on HRSD property and will have minimal impact on traffic. For the sewer pipeline work being installed in S. Willard Avenue and Downes Street, single lane traffic will be maintained throughout most of construction. Flagging may be used to help direct traffic as needed. Occasionally, block closures requiring minimal detours will be needed. Signage will be in place to direct traffic around any closures.
-
The contractor will ensure that access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services should not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
Work will typically take place Monday through Friday during daylight hours (7 a.m. - 5 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
-
Your sewer service may be temporarily interrupted while work is performed on the sewer lateral pipe that serves your property or the gravity sewer which accepts flow from your lateral. The contractor will notify you before work begins so you can plan appropriately. Sewer service typically will be restored within several hours. Your water service should not be affected by this project.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, etc. should be anticipated.
-
The contractor will store materials and supplies on the site of the existing Willard Avenue Pump Station, the new Willard Avenue Pump Station, and in areas of the street that are temporarily closed for construction. The contractor will transport them throughout the project area as they are needed.
-
Construction workers will not be allowed to park their personal vehicles in areas impacting residents or services such as mail and trash collection. Work trucks will be allowed to park within the active work zone.
-
The estimated cost for the project is $16 million and is financed by the wastewater treatment fees paid by HRSD customers.
-
Regular project updates are posted on the HRSD website at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the project.
FootnoteIf you have any questions, concerns or comments about the project, please feel free to contact: Shawn Maxfield, HRSD Public Information Specialist, at 757.833.7483 or smaxfield@hrsd.com
-
- Public Information Specialist:
-
Shawn Maxfield
757.833.7483 (Office)
- City of Hampton Contact:
- McCord Newsome
- Onsite Inspector (immediate/emergent concern):
- Larry Sumpter
- HRSD Project Manager:
- Ted Denny
- Additional Information:
- Projects@hrsd.com
-
- Director of Communications:
-
Leila Rice, APR
757.460.7056 (Office)
-
- Engineering Consultant Firm:
-
RK&K
Newport News, Virginia
- Engineering Consultant Project Lead:
-
Ryan Delo
- Contractor:
-
Kiewit Infrastructure South Co.
- Contractor Field Project Manager:
-
Jack Cosgrove