Construction Notice Update #20 for the City of Newport News - May 2024

-- Well Installation Update for Well #7 --

 

HRSD, your regional wastewater treatment utility, is undertaking improvements for the James River Treatment Plant SWIFT project. The construction at well site #7 (please see the map on the back for location information) will shift to 24-hour operations starting Friday, in order to complete this portion of work.

Read More


alertSubscribe

"Virginia Initiative Plant Tertiary Treatment Facility"
VIP SWIFT Tertiary Preliminary Engineering
HRSD Capital Improvement Program Project (GN016390)

 

Webpage Reviewed: March 2, 2026


HRSD, your regional wastewater treatment utility, is implementing the Sustainable Water Initiative for Tomorrow (SWIFT) Program. This Program will help reverse declining groundwater levels, significantly reduce the amount of nutrients such as nitrogen and phosphorus entering the Chesapeake Bay, and may reduce saltwater intrusion and land subsidence, thereby helping to ensure HRSD’s ability to protect public health and the environment in alignment with HRSD’s Promise and Vision.

The Virginia Initiative Plant (VIP) SWIFT Full Scale Implementation Program will be implemented in multiple phases and commonly referred to as the VIP SWIFT Tertiary Projects. The main purpose of the upgrade is to meet the 2032 James River total phosphorus reduction requirements, and it will be operational within the calendar year 2031. Additional upgrades could include VIP SWIFT Advanced Water Treatment and managed aquifer recharge implementation if future regulatory drivers necessitate further action. VIP SWIFT Tertiary Projects will be implemented using three Capital Improvement Projects (CIPs) through four project delivery stages: study, preliminary engineering, final design, and construction. The VIP suite of projects will include the Tertiary Facility Site work and the Tertiary Treatment Facility.      

This tertiary step is necessary to help meet regulatory requirements for nutrient reduction set forth by the EPA.

For more information about the integrated plan, please visit https://www.hrsd.com/epa-wet-weather-consent-decree-public-presentations.

Project Cost (Site Works): Approximately $32,000,000

Project Cost (Tertiary Treatment Facility): Approximately $324,000,000


Notices

 

April 11, 2025 - Media Advisory

Notice to Neighbors - April 2024

--Luxembourg Neighborhood--

 

Read More

Construction Notice Update #8a for the City of Newport News - April 2024

--Utility Work to Continue--

HRSD, your regional wastewater treatment utility, will continue work to replace a sanitary sewer pipeline located along Criston Drive from River Bend Court to Hancock Drive. This work should take place primarily during daytime hours.

Read More

Construction Notice Update #6c for the City of Newport News - April 2024

--Utility Work to Continue--

HRSD, your regional wastewater treatment utility, will work to replace a sanitary sewer pipeline in the intersection of HQ Way and the Yoder Plaza Shopping Center parking lot access road and along HQ Way to Jefferson Avenue (please see the map on the back of this notice). This work should take place primarily between the hours of 9 pm and 6 am.

Read More

Notice to Neighbors - April 2024

 

HRSD, your regional wastewater treatment utility, in coordination with the City of Hampton, is planning a project in your neighborhood to replace the existing HRSD sewer pipeline and manhole that is nearing the end of their useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.

Project Overview

Read More

Construction Notice Update #40 for the City of Chesapeake - April 2024

- Project Update -

 

Read More

Construction Notice Update #9A for the City of Chesapeake - April 2024

--On-street parking to be blocked off--

 

As mentioned in the previous Construction Notice Update #9, HRSD, your regional wastewater treatment utility, will continue work to install a sanitary sewer pipeline along Great Bridge Boulevard between Bainbridge Boulevard and Lincoln Road as part of the Great Bridge Boulevard Sanitary Sewer Improvements project. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Construction Notice Update #18 for the City of Newport News - April 2024

-- Riverview Farm Park Trails Construction Update Pile Driving Realignment Flax Mill Creek Trail --

 

HRSD, your regional wastewater treatment utility, is undertaking improvements for the James River Treatment Plant SWIFT project. The installation of over 1 mile of new trails adjacent to Riverview Farm Park and Menchville Marina and on HRSD’s and the City of Newport News’ property is underway. This work will typically take place during the hours of 7 am to 5 pm (Monday-Friday) in compliance with the project’s weekday work hours.

Read More