Construction Notice Update #4 for the City of Norfolk - May 2024
--Nighttime Work to Occur--
--Nighttime Work to Occur--
-- Utility Work to Occur --
HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline along Fontainebleau Crescent. This work should take place primarily between the hours of 7 a.m. to 7 p.m., Monday – Friday.
HAMPTON – Motorists are advised that HRSD crews will be performing sanitary sewer pipeline improvements at E. Mellen Street and N. Willard Avenue that require a closure between E. Howard Street and E. Mercury Boulevard. During this work traffic will follow a signed detour using E. Howard Street, N. Curry Street, and E. Mercury Boulevard as indicated on the map below. Motorists can use E. Mercury Boulevard to gain access to Fort Monroe. Local traffic will continue to have access to homes and businesses within the closed section of E.
-- Revised Early Morning Concrete Pour--
HRSD, your regional wastewater treatment utility, has revised the schedule for the early morning concrete pours at the Tabb Pressure Reducing Station & Offline Storage Facility. This revision has required HRSD to change the concrete pour hours and timeframe. This portion of the work will take place primarily between the hours of 4 a.m. to 5 p.m., Monday-Friday.
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday, but could include weekend work.
--Pump and Haul Work to Occur (Pump Station 114)--
--Pump and Haul Work to Occur (Pump Station 103)--
--Pump and Haul Work to Occur (Aluminum Avenue)--
--Project Update--
Our contractors have begun excavation on Rodgers Street and are scheduled to begin installation of new sewer pipeline in the second half of June. This pipeline work is expected to reach Holly Avenue by the beginning of July.
--Utility Work to Begin--
HRSD, your regional wastewater treatment utility, will begin the sanitary sewer rehabilitation work along Fox Hill Road and Beach Road from Old Buckroe Road to Westlawn Drive. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.