-
"Larchmont Area Sanitary Sewer Improvements"
Larchmont Area Sanitary Sewer Improvements
HRSD Capital Improvement Program Project (VP015320) -
HRSD and the City of Norfolk Department of Utilities are working together to begin a strategic program to replace, upgrade and relocate sanitary sewer pump stations and the connecting pipelines in the Larchmont Neighborhood. This program, made possible through wastewater collection and wastewater treatment fees, will protect public health by reducing the risk of sewer spills during large rainfall events.
HRSD and the City adopted the Larchmont Comprehensive Sanitary Sewer Master Plan in early 2020. In this plan, both parties agreed to replace aging wastewater infrastructure at the same time. Working together at every stage of the program to save customers money through shared design, construction efforts, and program management. By performing these needed infrastructure improvements simultaneously, the neighborhood experiences construction impacts only once, lessening the overall disruption to daily life.
Currently, the Larchmont Neighborhood is serviced with eight aging pump stations located throughout the area. Following a value engineering process conducted to ensure an improved and enhanced system at the lowest cost, the program will consist of consolidating four existing stations into three new stations while rehabilitating three existing stations with new pumps, structural rehabilitation and upgrading of electrical panels. A remaining pump station on Westwood Terrace was upgraded within the past few years and will remain in operation.
At the same time, construction to connect new sewer pipelines to the HRSD treatment plant will occur. Simultaneously constructing the pump stations and the pipelines will allow for contractors to complete their work as efficiently as possible and will minimize the overall timeline for disruptive construction work in the neighborhood.
The three new pump stations will be located at the following addresses:
- 6160 Rolfe Avenue
- 1101 Magnolia Avenue
- 933 Hanover Avenue
The three pump stations that will undergo rehabilitation are located at the following addresses:
- 1548 Buckingham Avenue
- 900 Jamestown Crescent
- 1228 Richmond Crescent
A map of both the new and rehabilitated locations and new sewer pipelines can be viewed under the Project Map tab.
We expect to release final designs, construction dates and project cost in late 2023 via this project website and at future civic and community group meetings.
-
Notices
January 22, 2024 - Notice to Neighbors
September 15, 2023 - Notice to Neighbors
August 2023 - Utilities Boring Notice
July 2023 - Construction Notice
-
April 19, 2024
Designs have been completed for several new or rehabilitated pump stations as part of the Larchmont Area Sanitary Sewer Improvements Program. The design renderings can be seen by visiting the “Larchmont Area Sanitary Sewer Improvements Project Update-Summer 2023” link in the Online Meetings & Events section of the webpage. Construction for these pump stations and accompanying sanitary sewer pipelines has not yet started but is estimated to begin in summer 2024. A construction schedule and updated information for the program will be presented at the Larchmont-Edgewater Civic League meeting on April 29, 2024. Design is nearing completion for the new pump station on Hanover Avenue and the rehabilitated pump station on Jamestown Crescent (see the Map Section for exact locations).
-
- Design:
-
Summer 2021 – Spring 2024
- Construction:
-
Anticipated Summer 2024 – Summer 2027
-
- Public Information Specialist:
- Lisa Bolen 757.460.7000 (Office)
- HRSD Project Manager:
- Tim Marsh
- Additional Information:
- Projects@hrsd.com
-
- Norfolk Dept. of Utilities:
- Jordan Stokes Public Information Specialist 757.404.5997 jordan.stokes@norfolk.gov
- HRSD Director of Communications:
- Leila Rice, APR 757.460.7056 (Office) 757.642.1321 (Cell)
-
- Engineering Consultant Firm:
-
Gannett Fleming, Virginia Beach, VA
- Norfolk Dept. of Utilities:
-
Dan Riley
Civil Engineer
757.266.9954
- City of Norfolk:
-
Freda Burns
Right of Way Administrator
757.636.3774
- Construction Manager:
-
Ulliman-Schutte