-
Subscribe
-
"Larchmont Area Sanitary Sewer Improvements"
Larchmont Area Sanitary Sewer Improvements
HRSD Capital Improvement Program Project (VP015320) -
HRSD is undertaking a strategic program to replace, upgrade and relocate sanitary sewer pump stations and the connecting pipelines in the Larchmont Neighborhood. This program, made possible through wastewater collection and wastewater treatment fees, will protect public health by reducing the risk of sanitary sewer overflows during large rainfall events.

HRSD and the City of Norfolk adopted the Larchmont Comprehensive Sanitary Sewer Master Plan in early 2020 which determined design, construction efforts, and program management. The program will now be managed and enacted by HRSD. Currently, the Larchmont Neighborhood is serviced with eight pump stations located throughout the area. The program will consist of replacing two existing HRSD stations with two new stations in the same service areas while rehabilitating three other existing HRSD stations with new pumps, structural rehabilitation, and upgrading of electrical panels.
At the same time as the HRSD pump station construction and rehabilitation, the installation of new sanitary sewer pipelines will occur. These new pipelines will connect the new pump stations to the existing sewer pipelines to allow the sewage to flow to the HRSD treatment plant. Simultaneously constructing the pump stations and the pipelines will allow for contractors to complete their work as efficiently as possible and will minimize the overall timeline for disruptive construction work in the neighborhood.
The two new pump stations will be located at the following addresses:- 1101 Magnolia Avenue
- 933 Hanover Avenue
The three pump stations that will undergo rehabilitation are located at the following addresses:
- 1548 Buckingham Avenue
- 1228 Richmond Crescent
- 900 Jamestown Crescent
A map of both the new and rehabilitated locations and new sewer pipelines can be viewed under the Project Map tab.
We expect to release final designs, construction dates and project cost in late 2024 via this project website and at future civic league meetings.
-
Notices
October 2025 - Construction Notice #11
September 2025 - Construction Notice #10
July 2025 - Construction Notice #9
May 2025 - Construction Notice #8
May 2025 - Construction Notice #7
May 2025 - Construction Notice #6
March 2025 - Construction Notice #5
March 2025 - Construction Notice #4
February 2025 - Construction Notice #3
January 2025 - Construction Notice #2
-
November 5, 2025
HRSD continued their work this month on several projects to replace several new or rehabilitated pump stations and pipelines as part of the Larchmont Area Sanitary Sewer Improvements Program. Expected work includes excavation at pump station sites followed by the construction of pump stations and installation of new equipment. New sanitary sewer pipelines will be installed via open-cut trench excavation.
Hanover Avenue Pump Station: Preparations for excavation have continued at the Hanover Avenue site with the further removal of on-site trees and the mobilization of equipment. The early stage of construction will consist of excavation to make space for the installation of a precast wet well.
Jamestown Pump Station: Following site clearing, work continues for the pump station rehabilitation on Jamestown Crescent with the mobilization for the installation of piles to provide foundation support during construction.
Magnolia Pump Station: The Magnolia Pump Station site work continues with the installation of masonry walls and framework for the pump station roof. Contractors will soon mobilize and prepare for the sewer pipe work at the site.Powhatan Pump Station: Following demolition of aged equipment, rehabilitation work continues at the Powhatan Pump Station site with the cleaning of the wet well and placement of new pumps in the dry well.
Richmond Crescent Pipeline Replacement: Restoration work on Richmond Crescent in the piepline installation area is now complete.
Richmond Crescent Pump Station: After removal/demolition of the current pump, piping, and electrical systems, our contractors installed new electrical conduit and cleaned the wet well at the Richmond Crescent Pump Station site as part of its rehabilitation.
The following general conditions can be expected during construction at program sites:- Your water and sewer service will not be disrupted.
- Through traffic will be detoured around active construction zones, but residents will still be able to access their homes. On-street parking will be closed in active pipeline construction zones.
- Construction update notices will be distributed to those in the affected areas throughout the project to provide updates of upcoming work; these notices will also be posted on this project webpage and NextDoor.
- Vibration monitors will be located onsite and near construction areas to minimize disruption. Alerts are provided to the contractor if the vibrations reach a particular level, and work will be stopped if these vibrations exceed federally established levels that may cause damage to residential structures.
- Some noise can be expected from excavation, backup alarms, diesel generators, motors, sheet pile driving, and other work.
- Dust control measures, such as temporary paving, frequent road cleaning, and/or application of water, will be enacted to reduce dust from becoming airborne.
- Construction work sites will be fenced in to protect from entry, and warning signs will be placed around pipeline work.
- Roadways and rights-of-way will be restored to their pre-construction structure and materials.
- Due to the nature of construction, work is weather and situation dependent, and dates are subject to change.
The most recent program information including expected work, project area expectations, construction schedules, and pump station renderings can be viewed in the Online Meetings & Events section of the webpage.
-
- Design:
-
Summer 2021 – Late 2024
- Construction:
-
Early 2025 – Summer 2027
-
-
The Larchmont Area Sanitary Sewer Improvement Program is a program by HRSD. The program is part of the recommended solution from the Larchmont Comprehensive Sanitary Sewer Master Plan that was adopted by HRSD and the City of Norfolk in early 2020 to serve the collective interests of the Larchmont Community, the City of Norfolk, and HRSD.
This program includes the demolition of two sanitary pump stations owned by HRSD, the construction of two new sanitary pump stations to be owned by HRSD, the rehabilitation of three HRSD pump stations, and the rehabilitation and replacement of approximately 1,470 feet of associated sewer pipelines in the Larchmont neighborhood.
-
The program is part of HRSD commitment to the Environmental Protection Agency (EPA) to reduce sanitary sewer overflows, pipe leakages, and interruptions in sewer service to customers due to aging infrastructure by 2028.
-
No. Although this program includes designing new pump stations and sewer lines that can withstand major rainfall events, it is not intended to collect or eliminate stormwater. The new pump stations and sanitary sewer lines will have increased capacity which will minimize sanitary sewer overflows (SSOs), but the system is not designed to be a stormwater collection and treatment system.
-
The program began construction in early 2025. Various phases of sewer pipeline installation and pump station construction will continue through late 2027.
-
You may see our personnel distributing notices and performing pre-construction assessments and our contractors preparing for program work. If access to a private property is needed, permission will be secured in advance with the property owner.
-
HRSD will provide advance notice via doorhangers ahead of all work taking place. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
Disruptions to traffic will be minimized, and in most cases, a single lane of traffic will be maintained. Through traffic will be detoured around active construction zones, but residents will still be able to access their homes. On-street parking will be closed in active pipeline construction zones.
-
The contractor will ensure that access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
Work will typically take place Monday through Friday during daylight hours (7 a.m. - 5 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
-
The work required to rehabilitate or replace sanitary sewer lines may require the lateral pipe serving your property to be removed from service and subsequently reinstated once work on the main sewer pipe has completed. This interruption of service will be temporary, and the contractor will notify you before work begins so you can plan accordingly. Sewer service typically will be restored within several hours. Your water service should not be affected by this project.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, and associated activities should be anticipated.
-
To protect residents during construction, vibration monitoring will be utilized throughout the project. Vibration monitoring will be carried out in advance of and during construction. Alerts are provided to the contractor, and work will be stopped if these vibrations exceed federally established levels that may cause damage to residential structures.
-
The estimated cost for the program is approximately $56.9 million and is financed by the wastewater and wastewater treatment fees paid by HRSD customers.
-
Outreach events (whether virtual or in-person) will be conducted periodically during the course of construction. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
- Public Information Specialist:
-
Lisa Bolen
757.460.7000 (Office)
- HRSD Project Manager:
- Kayla Rutherford
- Additional Information:
-
Projects@hrsd.com
-
- Norfolk Dept. of Utilities:
- Jordan Stokes Public Information Specialist 757.404.5997 jordan.stokes@norfolk.gov
- Chief of Communications:
-
Leila Rice, APR
757.460.7056 (Office)
-
- Engineering Consultant Firm:
-
Gannett Fleming, Virginia Beach, VA
- Construction Manager:
-
Ulliman-Schutte