Construction Notice Update #10 for the City of Chesapeake - September 2022
PROJECT UPDATES – SEPTEMBER 2022
Delay of 24-Hour Work and Perry Street Temporary Detour
On September 13th (Construction Notice
#9), we informed you that a planned period of 24-hour work was expected to occur between September 14th and September 17th.
planned period of 24-hour work was expected to occur between September 10th and September 13th. Due to repair issues, the 24-hour work was postponed again.
On August 18 (Construction Notice #6), we stated that two-periods of non-stop, 24-hour drilling would occur between August 23 and September 2. The first period of that drilling was completed on August 27.