Construction Notice Update #39 for the City of Chesapeake - March 2024
- Project Update -
- Project Update -
Jack and Bore Extension and Pump Station Upper Wall Pour
CHESAPEAKE – HRSD crews are installing sanitary sewer pipeline in Great Bridge Boulevard at the intersection of Neal Street. Work began on February 5 and is now expected to be completed in early March.
Upper Wall Pour Project Update – February 2024
February Project Update – February 2024
CHESAPEAKE – HRSD crews will install sanitary sewer pipeline in Great Bridge Boulevard at the intersection of Neal Street beginning as early as Monday, February 5 and could remain in place for up to two weeks.
--Road Closure at Great Bridge Boulevard & Neal Street--
HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline at the intersection of Neal Street and Great Bridge Boulevard. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday. The road closure/detour will be in place 24 hours/day.
Secondary Concrete Pour Project Update – January 2024
CHESAPEAKE – Motorists are advised that HRSD crews will be performing sanitary sewer pipeline repairs that require a road closure on Shell Road from the intersection of Hopewell Drive to Bay Oak Drive. This work will impact travel as follows:
January Project Update – January 2024