Construction Notice Update #6 for the City of Hampton - September 2022

--Utility Work to Occur--

 

HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline within Cameron Street between Libby Street and Bainbridge Avenue. The work within Cameron Street should take place between the hours of 8 a.m. to 6 p.m. Monday – Friday.

Read More

Construction Notice Update #6 for the City of Newport News - September 2022

-- Temporary Dog Park Closure --

 

HRSD, your regional wastewater treatment utility, is undertaking improvements at the City’s Gymnastic Center as part of the James River Treatment Plant SWIFT Improvements. This work should take place primarily between the hours of 7 a.m. to 6 p.m., Monday – Friday.

Read More

Construction Notice Update #11 for the City of Chesapeake - September 2022

PROJECT UPDATES – SEPTEMBER 2022

 

24-Hour Drilling Beginning Tuesday, 9/20

On September 13thimage (Construction Notice #9), we informed you that a planned period of 24-hour work was expected to occur between September 14th and September 17th.

Read More

Notice to Neighbors - September 2022

 

HRSD, your regional wastewater treatment utility, in coordination with the County of Middlesex, is planning a project to install a new collection system on General Puller Highway in the Village of Cooks Corner. The answers to some Frequently Asked Questions (FAQs) are provided here.

Project Overview

Read More

Notice to Neighbors - September 2022
Construction Notice Update #10 for the City of Chesapeake - September 2022

PROJECT UPDATES – SEPTEMBER 2022

 

Delay of 24-Hour Work and Perry Street Temporary Detour

On September 13th (Construction Noticeimage #9), we informed you that a planned period of 24-hour work was expected to occur between September 14th and September 17th.

Read More

Construction Notice Update #9 for the City of Chesapeake - September 2022

-- PROJECT UPDATES - SEPTEMBER 2022 --

 

Second Revised Notice of 24-Hour Work: Park Avenue

On September 8 (Construction Notice #8), we informed you that aimage planned period of 24-hour work was expected to occur between September 10th and September 13th. Due to repair issues, the 24-hour work was postponed again. 

Read More


alertSubscribe

"Nansemond Treatment Plant SWIFT Improvements"
Nansemond Treatment Plant Advanced Nutrient Reduction Improvements (ANRI), Phase II
Nansemond SWIFT Facility
Nansemond Recharge Wells (On Site)

HRSD Capital Improvement Program Project (NP013820, GN016380 & GN016381)

 

Webpage Reviewed: March 10, 2026


HRSD, your regional wastewater treatment utility, is implementing the Sustainable Water Initiative for Tomorrow (SWIFT) Program by constructing the second SWIFT Facility at the Nansemond Treatment Plant to produce a highly-treated water (SWIFT Water®) that meets drinking water standards and is suitable for recharge of the Potomac Aquifer. This Program will help reverse declining groundwater levels, significantly reduce the amount of nutrients such as nitrogen and phosphorus entering the Chesapeake Bay, and may reduce saltwater intrusion and land subsidence, thereby helping to ensure HRSD’s ability to protect public health and the environment in alignment with HRSD’s Promise and Vision.

Advanced Nutrient Reduction Improvements (ANRI):
Construction for the Advanced Nutrient Reduction Improvements project is ongoing. The installation of conductors to all three new electrical buildings and new motor control centers continues. Rough-in of power and control raceways, wire pulling, and termination preparations continue for Primary Clarifier 5. Stress testing is continuing for Aeration Tank 6 with the newly installed design modifications. Primary gravity thickener mechanisms are being installed in both tanks.

SWIFT Facility:
The basin floors are being formed for the SWIFT Influent Pump Station and Recharge Well Backflush Equalization Tank. Pile driving for deep foundations for the SWIFT Facility site is ongoing and is expected to continue through May 2026. Pile driving hours will remain between 7:00 a.m. and 5:00 p.m., Monday through Friday, with Saturday pile driving hours being 8:00 a.m. to 4:00 p.m.  Preparation of the contractor's staging area, office complex, and access roads to the recharge wells on the SWIFT Facility site continues.  Installation of SWIFT Water supply and backflush lines for Recharge Wells 4, 5, 6, and 7 continues.  24-hour drilling will occur at Well 10 during the month of March; the drilling is not expected to cause any excess noise other than a hum from a generator. Stormwater improvements continue for Pond 1 and Pond 2.

Together, the overall goal of the Nansemond projects is to help support growth and protect future generations. To learn more about SWIFT or to schedule a tour of the SWIFT Research Center (located at HRSD’s Nansemond Treatment Plant in Suffolk, VA), please visit www.hrsd.com/swift/.

Project Cost: Approximately $952,000,000


Notices

 

October 2025 - Project Introduction

August 2025 - Construction Notice #1

Notice to Neighbors - September 2022