Construction Notice Update #3 for the City of Newport News - August 2022
-- City’s Scenic Pier and Overlook Opening --
-- City’s Scenic Pier and Overlook Opening --
The County of Middlesex Virginia will be conducting a ‘Public Hearing’ on Wednesday, September 28, 2022, at 18:00h / 6:00pm at the Historic Courthouse, 865 General Puller Highway Saluda, VA 23149, into the Environmental Assessment for:
-- Work to Begin--
HRSD, your regional wastewater treatment utility, is undertaking a project to inspect and perform maintenance of the internal sanitary sewer piping and valves along Terminal Boulevard. This work should take place primarily between the hours of 8:00 a.m. to 5:00 p.m., Monday through Friday. This work can be weather and situation dependent and will not affect your water or sewer services.
-- PARK AVENUE PUMP STATION CONSTRUCTION UPDATES --
As early as Tuesday, September 6, 2022, the contractor for HRSD will begin work on Phase 2 of the South Norfolk Pump Stations and Sanitary Sewer Replacement Project.
-Project Update-
--Utility Work to Occur--
HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline within W. County Street between Woodland Road and Bainbridge Avenue. This work will mostly occur between the hours of 7 p.m. to 6 a.m. Sunday night - Friday morning due to City of Hampton permitting requirements associated with traffic control.
PROJECT UPDATES DUE TO WEATHER DELAY – AUGUST 2022
Continued Extended Work Hours:
To complete open-pit sewer work prior to the start of Rena B. Wright Elementary School’s 2022/2023 school year, Bridgeman Civil, the contractor for HRSD, will be extending work hours on Park Avenue to seven days per week (Sunday – Saturday), between the hours of 7 AM – Sunset (approximately 9 PM). This work schedule will be in place between now and September 6, 2022.
HRSD, your regional wastewater treatment utility, in coordination with the City of Newport News, is planning a project in your neighborhood to replace the existing HRSD sanitary sewer pipelines that are nearing the end of their useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.
Project Overview
HRSD, your regional wastewater treatment utility, in coordination with the City of Hampton, is planning a project in your neighborhood to replace existing HRSD and City sanitary sewer pipelines and public sewer service connections that are nearing the end of their useful life. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) are provided here.
--Work to Begin--
HRSD, your regional wastewater treatment utility, is undertaking an expedited pipeline replacement project to replace a sanitary sewer piping within the Western Branch Commons community. This work should take place primarily between the hours of 7:00 a.m. to 5:00 p.m., Monday through Friday. This work can be weather and situation dependent and should not affect your waterd or sewer services.