April 3, 2026
Pump Station Updates:
Concrete placements at the pump station 160 site at 2245 E. Washington Street continues. Approximately 70% of the concrete placement is complete. Regular concrete placement will continue every couple of weeks through May 2026. NOTE: Due to the duration of the concrete placements, these will typically be in the early morning hours.
Backfilling around the pump station is expected to begin in mid April and last for several weeks. During this time, there will be increased dump truck traffic in the area, but it will not require any road or lane closures on East Washington Street. Upon completion of the concrete and backfilling, the pump station will begin to take shape from a street view level. This vertical construction will continue through 2026.
At the Pump Station 159 site near Virgina Ham Drive, launch and receiving pits for the jack and bore pipelines are complete. The jack and bore casing has been installed, and pipe is being threaded through this casing over the next month. Further underground work will continue through early summer. Please see Construction Update Notice #4 under the "Project Advisories" section of the webpage for more information.
Sewer Pipeline Updates:
The microtunnel casing under the railroad tracks near Myrtle Street has been installed, and the installation of the sewer piping is ongoing. The entrance to Cypress Park near Arizona Avenue will have periodic closures.
Crews are installing a 16-inch sewer pipe along 58 Business (Portsmouth Boulevard) between Wilroy Road and Myrtle Street. This work will involve excavation of the roadway to install the pipeline underground, so traffic patterns will shift and will include periodic, temporary lane closures. Access to homes/businesses will be available. This section of work is expected to continue through summer 2026.
Additionally, sewer pipe installation continues on Hollywood Avenue and East Washington Street. This installation will occur with an open-cut trench method, meaning digging will occur from the street to install the pipe underground. Traffic patterns will include lane closures on Hollywood Avenue during construction. Access to homes/businesses will be available. This portion of the work is expected to be completed in June 2026, which will included final milling and paving of the disturbed areas.