Project Introduction - October 2025
Smoke Testing Notice for Suffolk - October 2025

--SUFFOLK--

Smoke testing of the sanitary sewer system will take place in your neighborhood in Suffolk in October.

Testing along your street:

November 17 - November 28, 2025

Read More

Construction Notice Update #4 for the City of Suffolk - October 2025

--Sewer Pipe Installation to Begin--

 

HRSD, your regional wastewater treatment utility, will begin work to install microtunnel pits in the Virginia Ham Drive/Portsmouth Boulevard area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Traffic Advisory - October 7, 2025

 

SUFFOLK – Motorists are advised that HRSD will begin work to install a sanitary sewer pipe on College Drive. This work will require a detour/lane shift of the west bound lane on College Drive between the southbound exit 8 ramp off I-664 and the traffic circle. The entrance and exit of Pointe Place will be closed during construction. The detour will begin as early as October 9 and continue until the end of February 2026. Motorists will need to follow the marked detour as indicated on the map below.

Read More

Construction Notice Update #3 for the City of Suffolk - September 2025

--Sewer Pipe Installation to Begin--

 

HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline in the Cypress Park/Hollywood area. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Construction Notice Update #1 for the City of Suffolk - August 2025

--Site Clearing to Begin--

HRSD, your regional wastewater treatment utility, is working to install a new sanitary sewer pump station and rehabilitate existing sanitary sewer and manholes in the Phoebus area. This work is being done to resolve capacity, operational, and maintenance issues that currently affect the existing pump station and pipes that are near the end of their useful life. The work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday and could include weekend work.

Read More

Construction Notice Update #2 for the City of Suffolk - July 2025

--Sewer Pipe Installation to Begin--

 

HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline on Portsmouth Boulevard between Proctor Street and Wilroy Road. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Construction Notice Update #1 for the City of Suffolk - May 2025

--E. Washington Street Pump Station Site Work to Begin--

 

HRSD, your regional wastewater treatment utility, will begin work to install a sanitary sewer pipeline and pump station on E. Washington Street. This work should take place primarily between the hours of 7 a.m. to 5 p.m., Monday – Friday.

Read More

Notice to Neighbors - April 2025

 

HRSD, your regional wastewater treatment utility, is planning a project in your area to replace an aging pump station with two new pump stations and to install new sanitary sewer pipelines to connect these new pump stations to the existing sewer system. This replacement project will also improve the system’s performance and ensure continued, reliable sewer service in the future. The answers to some Frequently Asked Questions (FAQs) can be found here.

Read More


alertSubscribe

"Hollywood Area Sewer Pipeline & Pump Station Replacement"
Suffolk Pump Station Replacement
HRSD Capital Improvement Program Project (NP010620)

 

Webpage Reviewed: December 5, 2025


HRSD is undertaking a project to replace an aging pump station (PS-135) and its associated gravity sanitary sewer pipeline that runs along the banks of Shingle Creek between East Washington Street and Wilroy Road. This project will abandon / demolish the aged previous system and install a new modern system that will help ensure HRSD’s ability to protect public health and the environment for decades to come. The project includes:

  • A new 16-inch sewer pipe (force main): Located along Portsmouth Boulevard from the intersection of Portsmouth Boulevard and Wilroy Road to the junction with the 8-inch sewer pipe at Myrtle Street. The sewer pipe continues from the intersection of Portsmouth Boulevard and Myrtle Street south towards Cypress Point Park, and this section will be constructed via a trenchless crossing that does not require as much digging. The rest of the new sewer pipe will continue south through the Cypress Point Park, east along Kentucky Avenue, before continuing south along Hollywood Avenue and East Washington Street to the future pump station (PS-160) site and will be constructed via open-cut method that will require excavation
  • A new 8-inch sewer pipe (force main): Located along Portsmouth Boulevard from Myrtle Street to the future pump station (PS-159) site on Virginia Ham Drive. This installation includes two trenchless crossings. The remainder of the pipe installation will be via open-cut method that will require excavation
  • A new pump station, PS-159: Located near the intersection of Portsmouth Boulevard and Virginia Ham Drive
  • A new pump station, PS-160: Located at 2245 East Washington Street

To protect structures during construction, vibration monitoring will be utilized throughout the project. Vibration monitoring will be carried out in advance of and during construction. Alerts are provided to the contractor, and work will be stopped if these vibrations exceed federally established levels that may cause damage to residential structures.