"Boat Harbor Treatment Plant Conversion and Transmission"
Boat Harbor Treatment Plant Pump Station Conversion 
Boat Harbor Treatment Plant Transmission Force Main Section 1 (Subaqueous)
Boat Harbor Treatment Plant Transmission Force Main Section 2 (Land)
HRSD Capital Improvement Program Project (BH015700, BH015710 & BH015720)


HRSD is closing its Boat Harbor Treatment Plant in Newport News to further reduce nutrients discharged to the James River Basin, which will support local water quality and Chesapeake Bay restoration efforts. A new pumping station facility will be constructed at the Boat Harbor location, and wastewater will be pumped to HRSD’s Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River. A significant portion of the treated water will undergo additional advanced treatment to meet drinking water quality standards to produce SWIFT Water™. To connect HRSD’s Boat Harbor and Nansemond facilities, construction of 31,000 feet of pipe is required. The pipe varies in size from 42 inches to 54 inches. The section installed under the Newport News Shipping Channel using horizontal direction drilling is 42 inches. The pipe then expands to 54 inches before reducing back down to 48 inches as the flow enters the Nansemond Treatment Plant for further treatment.

This work includes three separate projects: Boat Harbor Pump Station Conversion, Boat Harbor Underwater Transmission Pipe Installation, and Nansemond Treatment Plant Pipe Installation. To see more information, please check below in the “Update” section for a link to each project, including FAQ’s for each.

For more information on the SWIFT process, please visit www.hrsd.com/swift.


alertSubscribe

"Boat Harbor Pump Station Conversion"
Boat Harbor Treatment Plant Pump Station Conversion
Boat Harbor Treatment Plant Pump Station Conversion Site Improvements
HRSD Capital Improvement Program Project (BH015700 & BH015701)


As part of the Sustainable Water Initiative for Tomorrow (SWIFT) program, HRSD will pump wastewater from Newport News to its Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River.  A significant portion of the treated water will undergo additional advanced treatment to produce SWIFT WaterTM which will meet drinking water quality standards. This will further reduce nutrients discharged to the James River Basin and support local water quality and Chesapeake Bay restoration efforts. The existing Boat Harbor Treatment Plant will be closed and replaced with the Boat Harbor Pump Station. 

Project Cost: Approximately $196.5 million


Notices

 

October 2023 - Construction Notice Update #1

October 2023 - Notice to Neighbors


alertSubscribe

"Boat Harbor Land Transmission Pipe Installation"
Boat Harbor Treatment Plant Transmission Force Main Section 2 (Land)
HRSD Capital Improvement Program Project (BH015720)


As part of the Sustainable Water Initiative for Tomorrow (SWIFT) program, HRSD will pump wastewater from Newport News to its Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River. A significant portion of the treated water will undergo additional advanced treatment to produce SWIFT WaterTM which will meet drinking water quality standards. This will further reduce nutrients discharged to the James River Basin and support local water quality and Chesapeake Bay restoration efforts. To connect HRSD’s Boat Harbor Underwater Transmission Pipeline to Nansemond facilities, construction of a 7,000-foot pipeline on land is also required. Pipes to be installed in this area include a 48-inch diameter pipe for wastewater and pipes that will convey treated water to recharge wells that will be installed in the area.

Project Cost: Approximately $38 million


Notices

 

October 7, 2025 - Traffic Advisory

August 15, 2025 - Traffic Advisory

August 14, 2025 - Traffic Advisory

July 18, 2025 - Traffic Advisory

July 8, 2025 - Traffic Advisory

April 2025 - Construction Notice #1

April 2025 - Notice to Neighbors

November 2022 - Public Notice of Agency Review Period


alertSubscribe

"Boat Harbor Underwater Transmission Pipe Installation"
Boat Harbor Treatment Plant Transmission Force Main Section 1 (Subaqueous)
HRSD Capital Improvement Program Project (BH015710)


As part of the Sustainable Water Initiative for Tomorrow (SWIFT) program, HRSD will pump wastewater from Newport News to its Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River.  A significant portion of the treated water will undergo additional advanced treatment to produce SWIFT WaterTM which will meet drinking water quality standards. This will further reduce nutrients discharged to the James River Basin and support local water quality and Chesapeake Bay restoration efforts. To connect HRSD’s Boat Harbor and Nansemond facilities, construction of 24,000 foot of pipe below the bottom of the James River is required.

Project Cost: Approximately $136 million


Notices
Notice to Neighbors - April 2021
Construction Notice Update #12 for the City of Newport News - April 2021

--Abandonment of Existing Old Sewer Pipe--

 

Read More

Construction Notice Update #1 for the City of Chesapeake - April 2021

--Work to Begin--

HRSD, your regional wastewater treatment utility, will begin work to install a new sanitary sewer air vent at the intersection of Berkley Avenue and Wilson Road. This work should take place primarily between the hours of 8 a.m. to 6 p.m., Monday – Friday.

WHAT YOU NEED TO KNOW:

Read More