VIRGINIA BEACH – HRSD has received $8.7 million in funding from the Coronavirus Aid, Relief and Economic Security (CARES) Act program to help customers faced with past-due bills resulting from COVID-19-related financial hardships. Funds will be provided on a first-come, first serve basis and must be disbursed by January 29, 2021.
-
Subscribe
-
"Larchmont Area Sanitary Sewer Improvements"
Larchmont Area Sanitary Sewer Improvements
HRSD Capital Improvement Program Project (VP015320)Webpage Reviewed: February 13, 2025
-
HRSD is undertaking a strategic program to replace, upgrade and relocate sanitary sewer pump stations and the connecting pipelines in the Larchmont Neighborhood. This program, made possible through wastewater collection and wastewater treatment fees, will protect public health by reducing the risk of sanitary sewer overflows during large rainfall events.

HRSD and the City of Norfolk adopted the Larchmont Comprehensive Sanitary Sewer Master Plan in early 2020 which determined design, construction efforts, and program management. The program will now be managed and enacted by HRSD. Currently, the Larchmont Neighborhood is serviced with eight pump stations located throughout the area. The program will consist of replacing two existing HRSD stations with two new stations in the same service areas while rehabilitating three other existing HRSD stations with new pumps, structural rehabilitation, and upgrading of electrical panels.
At the same time as the HRSD pump station construction and rehabilitation, the installation of new sanitary sewer pipelines will occur. These new pipelines will connect the new pump stations to the existing sewer pipelines to allow the sewage to flow to the HRSD treatment plant. Simultaneously constructing the pump stations and the pipelines will allow for contractors to complete their work as efficiently as possible and will minimize the overall timeline for disruptive construction work in the neighborhood.
The two new pump stations will be located at the following addresses:- 1101 Magnolia Avenue
- 933 Hanover Avenue
The three pump stations that will undergo rehabilitation are located at the following addresses:
- 1548 Buckingham Avenue
- 1228 Richmond Crescent
- 900 Jamestown Crescent
A map of both the new and rehabilitated locations and new sewer pipelines can be viewed under the Project Map tab.
We expect to release final designs, construction dates and project cost in late 2024 via this project website and at future civic league meetings.
-
Notices
February 2026 - Construction Notice #13
February 2026 - Construction Notice #12
October 2025 - Construction Notice #11
September 2025 - Construction Notice #10
July 2025 - Construction Notice #9
May 2025 - Construction Notice #8
May 2025 - Construction Notice #7
May 2025 - Construction Notice #6
March 2025 - Construction Notice #5
March 2025 - Construction Notice #4
February 2025 - Construction Notice #3
January 2025 - Construction Notice #2
-
February 5, 2026
HRSD continued their work this month on several projects to replace several new or rehabilitated pump stations and pipelines as part of the Larchmont Area Sanitary Sewer Improvements Program. Expected work includes excavation at pump station sites followed by the construction of pump stations and installation of new equipment. New sanitary sewer pipelines will be installed via open-cut trench excavation.
Hanover Avenue Pump Station: Construction of the new control building continues. Crews have completed the concrete pour for the top slab for the building. Over the next few weeks, crews will begin masonry construction of the new exterior walls.
Jamestown Pump Station: Rehabilitation construction continues at the Jamestown Crescent Pump Station site. Upcoming work will include excavation for the new control building and installation of under-slab bypass piping.
Magnolia Pump Station: Site work continues at the Magnolia Pump Station with the recent installation of a new exterior metal platform. Upcoming work will include the installation of the permanent bypass pump, odor control systems, and new mechanical process piping. Exterior siding will be installed over the next few weeks. Electrical work inside the new control building is progressing as materials are received.Powhatan Pump Station: Rehabilitation efforts at the Powhatan Pump Station will continue with further installation of electrical equipment and wiring. Crews are now beginning sitework with the installation of new precast concrete structures.
Richmond Crescent Pump Station: Rehabilitation work continues at the Richmond Crescent Pump Station with the installation of new wiring, heaters, access hatches, and piping.
The following general conditions can be expected during construction at program sites:- Your water and sewer service should not be disrupted.
- Through traffic will be detoured around active construction zones, but residents will still be able to access their homes. On-street parking will be closed in active pipeline construction zones.
- Construction update notices will be distributed to those in the affected areas throughout the project to provide updates of upcoming work; these notices will also be posted on this project webpage and NextDoor.
- Vibration monitors are located onsite and near construction areas to minimize disruption. Alerts are provided to the contractor if the vibrations exceed a particular level, and work will be stopped and reassessed if these vibrations exceed established sustained levels that may cause damage to residential structures.
- Some noise can be expected from excavation, backup alarms, diesel generators, motors, sheet pile driving, and other work.
- Dust control measures, such as temporary paving, frequent road cleaning, and/or application of water, will be enacted to reduce dust from becoming airborne.
- Construction work sites will be fenced in to protect from entry, and warning signs will be placed around pipeline work.
- Roadways and rights-of-way will be restored to their pre-construction structure and materials.
- Due to the nature of construction, work is weather and situation dependent, and dates are subject to change.
The most recent program information including expected work, project area expectations, construction schedules, and pump station renderings can be viewed in the Online Meetings & Events section of the webpage.
-
- Design:
-
Summer 2021 – Late 2024
- Construction:
-
Early 2025 – Summer 2027
-
-
The Larchmont Area Sanitary Sewer Improvement Program is a program by HRSD. The program is part of the recommended solution from the Larchmont Comprehensive Sanitary Sewer Master Plan that was adopted by HRSD and the City of Norfolk in early 2020 to serve the collective interests of the Larchmont Community, the City of Norfolk, and HRSD.
This program includes the demolition of two sanitary pump stations owned by HRSD, the construction of two new sanitary pump stations to be owned by HRSD, the rehabilitation of three HRSD pump stations, and the rehabilitation and replacement of approximately 1,470 feet of associated sewer pipelines in the Larchmont neighborhood.
-
The program is part of HRSD commitment to the Environmental Protection Agency (EPA) to reduce sanitary sewer overflows, pipe leakages, and interruptions in sewer service to customers due to aging infrastructure by 2028.
-
No. Although this program includes designing new pump stations and sewer lines that can withstand major rainfall events, it is not intended to collect or eliminate stormwater. The new pump stations and sanitary sewer lines will have increased capacity which will minimize sanitary sewer overflows (SSOs), but the system is not designed to be a stormwater collection and treatment system.
-
The program began construction in early 2025. Various phases of sewer pipeline installation and pump station construction will continue through late 2027.
-
You may see our personnel distributing notices and performing pre-construction assessments and our contractors preparing for program work. If access to a private property is needed, permission will be secured in advance with the property owner.
-
HRSD will provide advance notice via doorhangers ahead of all work taking place. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
Disruptions to traffic will be minimized, and in most cases, a single lane of traffic will be maintained. Through traffic will be detoured around active construction zones, but residents will still be able to access their homes. On-street parking will be closed in active pipeline construction zones.
-
The contractor will ensure that access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
Work will typically take place Monday through Friday during daylight hours (7 a.m. - 5 p.m.). However, there may be times when extended hours, work at night, or weekend work may be necessary.
-
The work required to rehabilitate or replace sanitary sewer lines may require the lateral pipe serving your property to be removed from service and subsequently reinstated once work on the main sewer pipe has completed. This interruption of service will be temporary, and the contractor will notify you before work begins so you can plan accordingly. Sewer service typically will be restored within several hours. Your water service should not be affected by this project.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the project.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, and associated activities should be anticipated.
-
To protect residents during construction, vibration monitoring will be utilized throughout the project. Vibration monitoring will be carried out in advance of and during construction. Alerts are provided to the contractor, and work will be stopped if these vibrations exceed federally established levels that may cause damage to residential structures.
-
The estimated cost for the program is approximately $56.9 million and is financed by the wastewater and wastewater treatment fees paid by HRSD customers.
-
Outreach events (whether virtual or in-person) will be conducted periodically during the course of construction. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
- Public Information Specialist:
-
Lisa Bolen
757.460.7000 (Office)
- HRSD Project Manager:
- Kayla Rutherford
- Additional Information:
-
Projects@hrsd.com
-
- Norfolk Dept. of Utilities:
- Jordan Stokes Public Information Specialist 757.404.5997 jordan.stokes@norfolk.gov
- Chief of Communications:
-
Leila Rice, APR
757.460.7056 (Office)
-
- Engineering Consultant Firm:
-
Gannett Fleming, Virginia Beach, VA
- Construction Manager:
-
Ulliman-Schutte
-
Subscribe
-
"South Norfolk Pump Stations and Sanitary Sewer Replacement Project"
Ferebee Avenue Pump Station Replacement
Sanitary Sewer Project 1950 - Part 1
Sanitary Sewer Project 1950 - Part 2
Park Avenue Pump Station ReplacementHRSD Capital Improvement Program Project (VP014010, VP014021, VP014022 & VP018000)
Webpage Reviewed: February 5, 2025
-
In Summer 2022, HRSD began a multi-year project to replace critical aging infrastructure in the South Norfolk community. This project consists of three phases that will replace two aging sanitary sewer pump stations and their associated sanitary sewer pipes. To improve sewer system reliability and provide for future capacity, the pump stations will be demolished and rebuilt on adjacent lots. The pipelines between these two pump stations are being replaced and, in certain cases, rehabilitated. For the pump station and sewer pipe locations, please refer to the Project Map.
- Park Avenue Pump Station: The current pump station is located at 503 Park Avenue. Once the new pump station is built on the corner of Park Avenue and Porter Street, the former pump station will be demolished. For artist renderings on what the new pump station will look like, please view the presentation in the Online Meetings & Events section of this webpage.
- Sanitary Sewer Pipeline Replacement: The pipelines that will connect to the two pump stations will be replaced or rehabilitated. This work will occur along Park Avenue, Rodgers Street, Byrd Avenue, and Bainbridge Boulevard.
- Ferebee Avenue Pump Station: The current pump station is located across from Ferebee Avenue at 2812 Bainbridge Boulevard. Once the pump station is built on the adjacent lot at 2900 Bainbridge Boulevard, the former pump station will be demolished. For artist renderings on what the new pump station will look like, please view the presentation in the Online Meetings & Events section of this webpage.
Project Cost: Approximately $35,800,000
-
Notices
February 2026 - Construction Notice Update #69
January 2026 - Construction Notice Update #68
November 2025 - Construction Notice Update #67
October 2025 - Construction Notice Update #66
October 2025 - Construction Notice Update #65
September 2025 - Construction Notice Update #64
September 2025 - Construction Notice Update #63
August 2025 - Construction Notice Update #62
August 2025 - Construction Notice Update #61
July 2025 - Construction Notice Update #60
July 2025 - Construction Notice Update #59
June 2025 - Construction Notice Update #58
June 2025 - Construction Notice Update #57
May 2025 - Construction Notice Update #56
April 2025 - Construction Notice Update #55
March 2025 - Construction Notice Update #54
March 2025 - Construction Notice Update #53
March 2025 - Construction Notice Update #52
February 2025 - Construction Notice Update #51
January 2025 - Construction Notice Update #50
-
February 5, 2026
Dust control measures such as paving, frequent road cleaning and/or application of water will be enacted to reduce dust from becoming airborne in our construction areas. After construction, roadways and rights-of-way will be restored to their pre-construction structure and materials.
Bainbridge Boulevard Pipeline Work Update:
Sewer pipe installation is currently occurring on Bainbridge Boulevard between Wilbur Avenue and Wright Avenue, moving south toward Swain Avenue, with excavation recently taking place near Orville Avenue. During pipeline construction, Bainbridge Boulevard will be closed in the northbound lane around the construction areas between Wilbur Avenue and Wright Avenue. Residents on Wilbur, Orville, and Wright avenues can access their homes via local traffic routes off Bainbridge Boulevard onto the parallel streets of Byrd Avenue and Hughes Avenue, followed by the cross street of Chamberlain Avenue.
The pipeline construction is planned to be completed by summer 2027.
Ferebee Avenue Pump Station Update:
Our contractors continue to prepare for the pouring of the top slab of the station following the placement of reinforcing steel. Additional work has included the pre-pour positioning of electrical conduits and backfilling around the station’s perimeter.
During material deliveries, soil/debris removal, or concrete pours at the pump station site, southbound traffic on Bainbridge Boulevard may be reduced to one lane for the safety of our contractor crews and customers.
Final pump station construction is expected to be completed in 2027.
Park Avenue Pump Station Construction Update:
Start-up preparation activities have continued at the Park Avenue Pump Station including grading of the site. Construction is ongoing through spring 2026.
Perry Street Pipeline Update:
Further sewer pipeline installation southward on Perry Street is expected to take place during summer 2026.
-
All work will be confined to HRSD property and road rights-of-way.
Impacted roads will include:
- Park Avenue
- Rodgers Street
- Byrd Avenue
- Bainbridge Boulevard
-
- Park Avenue Pump Station Construction:
-
Fall 2022 - Spring 2026
- Sanitary Sewer Pipeline Construction:
-
Summer 2022 – Summer 2027
- Ferebee Pump Station Construction:
-
Early 2025 – Late 2027
-
-
The project is necessary in order to provide reliable conveyance of sewage in the South Norfolk area. Replacing the existing pump stations with new modernized infrastructure will help to ensure wastewater capacity is adequate and will optimize HRSD’s ability to protect public health and the environment for decades to come.
-
No. Although this program includes designing new pump stations and sewer lines that can withstand flooding from major storm events, it is not intended to collect or eliminate storm water. The new pump stations and sanitary sewer lines will have increased capacity which will minimize sanitary sewer overflows (SSOs), but the system is not designed to be a stormwater collection and treatment system.
-
During the design phase of this project (ongoing through Spring 2024), surveyors or contractors may be seen working in the area. All survey work during this time will be completed in public rights-of-way. If access to a private property is needed, permission will be secured in advance with the property owner.
-
Disruptions to traffic will be minimized, and, in most cases, a single lane of traffic will be maintained. Some road closures will be necessary, and detours will be in place. Access to homes/businesses will be available.
-
The contractor will ensure that access to residences and at least one entrance to businesses will be maintained throughout construction. Trash and mail services will not be affected. If necessary, the contractor will move trash containers from within a work zone to an area accessible for pickup and will be responsible for returning them to each residence.
-
To protect residential structures during construction, over 35 vibration monitoring locations will be installed for use throughout the installation of sanitary sewer lines. Vibration monitoring will be carried out in advance of and during construction. Alerts are provided to contractor if the vibrations reach a particular level and work will be stopped if these vibrations exceed federally-established levels that may cause damage to residential structures.
-
For the sanitary sewer pipeline work occurring on Park Avenue, construction may occur Monday through Saturday between the hours of 7 a.m. and 7 p.m. However, for the other phases of the project, work will typically take place Monday through Friday during daylight hours (8 a.m. - 4 p.m.). There may be times when extended hours, work at night, or weekend work is necessary, but changes in work hours will be announced ahead of time to impacted individuals.
-
Your sewer service will be temporarily interrupted if work is to be performed on the sewer lateral pipe that serves your property. The contractor will notify you before your lateral is to be rehabilitated so you can plan appropriately. Sewer service typically will be restored within several hours. Your water service should not be affected by this program.
-
Where sewer and lateral pipes are dug up, asphalt, curb, gutters, driveway aprons, and grass will be removed and then restored upon completion of the program.
-
The typical construction noises such as equipment engines, back-up alarms, materials being delivered, diesel generators, air compressors, sawing, etc. should be anticipated during daylight hours (8 a.m. - 4 p.m.). If night work is to occur, affected residents will receive a notification ahead of the work.
-
An off-site storage area in the program vicinity will be used for the storage of most of the equipment and supplies. Some supplies may be contained within the active work zone, in the public right-of way.
-
Construction workers will not be allowed to park their personal vehicles on the public streets. However, work trucks will be allowed to park within the active work zone.
-
The estimated cost for the program is $35.8 million and is financed by the wastewater and wastewater treatment fees paid by HRSD customers.
-
The project website will be updated on a monthly basis regarding any schedule changes or project updates and can be accessed at www.hrsd.com/construction-status. You may also sign up at www.hrsd.com/subscriptions to receive an email notification whenever the website has an update about the program.
-
- Public Inquiries
-
Lisa Bolen
757.460.7000 (Office)
- Project Manager
- Nick Taschner
- Additional Information
-
Projects@hrsd.com
-
- Chief of Communications
-
Leila Rice, APR
757.460.7056 (Office)
-
- Engineering Consultant Firm:
-
Gannett Fleming, Virginia Beach, VA
- Contractor:
-
Bridgeman Civil (Sewer Pipe Installation)
- Contractor:
-
Shaw Construction (Park Avenue Pump Station)
Shaw Project Manager: Chuck Thompson
- Contractor:
-
ACE Service Inc. (Ferebee Pump Station)
Where Can I Go For More Information?
James River Virtual Open House Video
What will Riverview Farm Park look like after construction?
What will Riverview Farm Park look like after construction?
- Final restoration of SWIFT Upgrades by late 2025
- All new trails open by 2026
- Well house buildings with amenities, bathrooms, educational information, benches; finished by late 2025
- HRSD Administration Building provides public meeting space, restrooms and parking