alertSubscribe

"Kiln Creek/Patrick Henry Mall Area Sewer Pipe Replacement"
Jefferson Avenue Interceptor Force Main Replacement Phase III
HRSD Capital Improvement Program Project (JR011730)

 

Webpage Reviewed: April 2, 2026


HRSD is undertaking a project to replace and upgrade sewer pipes in the Kiln Creek/Patrick Henry Mall Area. Please refer to the project map to see the roads affected. This effort will increase operational flexibility, reduce system pressures, and improve performance within the sewer system. A micro-tunnel will be used to install the new sewer pipes under I-64 without cutting open the road above it. The remainder of the new sewer pipes will be installed in a trench. Pavement restoration of the roadways affected by installation of the sewer pipes will occur once the installation is complete. The existing sewer pipe will not be needed once the sewer pipes have been installed and will be abandoned in place. This means the abandoned pipes will be filled with a cementitious-like material so they can remain underground. This prevents more area from having to be dug up and disturbed.

Project Cost: Approximately $21.5 Million



alertSubscribe

"Atlantic Treatment Plant Odor Control Improvements"
HRSD Capital Improvement Program Project (AT015800, AT015900, AT016000 and AT016100)

 

Webpage Reviewed: March 2, 2026


ATP

 

HRSD’s Atlantic Treatment Plant is located at 645 Firefall Drive in Virginia Beach, Virginia and was initially brought online in 1983. The plant was expanded in 2009 and currently has an average daily treatment capacity of 54 million gallons a day (mgd), with an ultimate build-out capacity of 72 mgd. The plant is staffed 24 hours per day. Administrative hours are 6:30 am - 3:00 pm, Monday - Friday.

Atlantic Treatment Plant Master Plan

The Atlantic Treatment Plant Reliability and Odor Control Improvements (ROCI) Program includes a series of projects designed to reduce odors from the facility by upgrading the odor control facilities and enhancing the reliability of solids processing systems that produce the most significant odors. Major improvements include new odor treatment systems, new digester covers to better contain odors, a new enclosed flare to improve combustion of biogas, and new solids processing facilities to reduce outages that can impact offsite odors.

HRSD has selected a Construction Management firm to implement the improvements in a multi-phase program that will streamline the construction process and allow program elements to be completed based on their priority and complexity. Complex elements with long material deliveries, extensive permitting requirements, and challenging construction requirements are expected to be completed by 2028. However, many of the improvements can and will be completed sooner. The project phases include:

  • Emergency and Near-Term Improvements - HRSD has issued an emergency declaration to allow expedited procurement and construction on multiple elements of the project.
    • Odor neutralization around the digesters has been implemented to reduce the strength of the odors while the design and construction of new digesters covers is being performed
    • Odor neutralization around the solids storage will be operated to reduce the strength of the odors while new solids handling and storage facilities are being constructed.
    • Odor Control Station (OCS) optimization will improve odor removal performance. This means the existing equipment will be fine-tuned until it is operating at its peak. This includes adjusting chemical feed rate, blower speeds, and pumps until the hydrogen sulfide concentrations are below detectable levels.
    • Carbon treatment systems downstream of the existing odor control systems will provide a second stage of treatment to further reduce odors.
    • Replace existing digester mixers to eliminate the process upsets that cause odor events.
    • New enclosed flare to enhance combustion of odorous biogas.
  • Early Work Packages – In addition to the emergency and near-term improvements, other items will have an accelerated design and early procurement of equipment to expedite the completion of some of the more critical solids reliability items, including redundant solids handling systems (e.g. conveyor, storage silo, etc.) and demolition of structures to make space for new long-term odor treatment systems.
  • Long-Term Odor Facilities – Replacement of aging odor control equipment.
  • Solids Processing Improvements – Some of the largest and most complex portions of the project include new digester covers, a redundant thermal hydrolysis (THP) system, and new gravity thickeners.

To review the most recent program status, please continue to the UPDATE section below.



alertSubscribe

"Great Bridge Boulevard Sanitary Sewer Improvements"
Washington District Pump Station Area Sanitary Sewer Improvements
HRSD Capital Improvement Program Project (AT013000)

 

Webpage Reviewed: April 2, 2026


The project consists of the installation of sewer pipeline that ranges in various sizes from 8 inches to 24 inches. Both gravity sewer pipes and force main sewer pipes will be installed as well as the installation of precast manholes and the rehabilitation of other manholes. Additionally, a 42-inch guided auger bore under the railroad will occur. A guided bore allows pipeline to be guided into place underground without cutting open the road above it, so the railroad will remain undisturbed. Some sanitary sewer lateral replacement and reconnections will occur as well. The existing pipe, manholes, and pump station outfall that are no longer needed will be abandoned in place. This means the abandoned pipes will be filled with a cementitious-like material so they can remain underground. This prevents more area from having to be dug up and disturbed. Pavement restoration of the affected roadways will occur once the sewer installation is complete. These improvements will replace aging infrastructure, increase capacity, and improve performance within HRSD’s sanitary sewer system.



alertSubscribe

"Hog Island Pump Station & Sanitary Sewer Installation"
Surry Force Main and Pump Station – Dominion Power Extension
HRSD Capital Improvement Program Project (SU010400)

 

Webpage Reviewed: March 2, 2026


HRSD is undertaking a project to construct a new pump station and sanitary sewer pipeline to convey sewage flows generated at the Dominion Energy Surry Nuclear Power Station to the existing Mt. Ray Pump Station located on Mt. Ray Drive in Surry County. The project will convey only domestic sewage flows (restrooms, kitchens, etc.) from the Dominion facility. The Hog Island pump station will be constructed within the property of the Surry Nuclear Power Station property, and the sewer pipeline will be aligned along the Dominion Energy easement from the Power Station, crossing Route 10 to Mt. Ray. The project will allow closure of the existing sewage treatment plant serving the Power Station.

Project Cost: $9,000,000


Notices

 

December 2024 - Notice to Neighbors


alertSubscribe

Portsmouth Sanitary Sewer Inflow & Infiltration Reduction
VIP Service Area I/I Reduction Phase I & III - Portsmouth
HRSD Capital Improvement Program Project (VP018301/VP018303)

 

Webpage Reviewed: March 2, 2026


HRSD, in coordination with the City of Portsmouth, is undertaking a project to inspect and rehabilitate or replace City sanitary sewer infrastructure at two primary locations. A program of High Priority Projects will be constructed through 2030 as part of HRSD’s Regional Wet Weather Management Plan. Projects were selected based on their ability to provide the greatest environmental benefits. Rehabilitation of sanitary sewer within two areas of the City of Portsmouth are part of the larger High Priority program. This work is ultimately being conducted to reduce the risk of sanitary sewer overflows during heavy rain events such as Nor’easters or hurricanes. Please see the Project Map in the “Project Map” tab below to view a map of the entire project area in Portsmouth. To see more detailed maps of the two sections to be assessed, please click here.

Project Cost: $29,668,000


Notices

 

August 2024 - Smoke Testing Notice

October 2023 - Smoke Testing Notice

August 2023 - Smoke Testing Notice


alertSubscribe

"Nansemond Treatment Plant SWIFT Improvements"
Nansemond Treatment Plant Advanced Nutrient Reduction Improvements (ANRI), Phase II
Nansemond SWIFT Facility
Nansemond Recharge Wells (On Site)

HRSD Capital Improvement Program Project (NP013820, GN016380 & GN016381)

 

Webpage Reviewed: April 2, 2026


HRSD, your regional wastewater treatment utility, is implementing the Sustainable Water Initiative for Tomorrow (SWIFT) Program by constructing the second SWIFT Facility at the Nansemond Treatment Plant to produce a highly-treated water (SWIFT Water®) that meets drinking water standards and is suitable for recharge of the Potomac Aquifer. This Program will help reverse declining groundwater levels, significantly reduce the amount of nutrients such as nitrogen and phosphorus entering the Chesapeake Bay, and may reduce saltwater intrusion and land subsidence, thereby helping to ensure HRSD’s ability to protect public health and the environment in alignment with HRSD’s Promise and Vision.

Advanced Nutrient Reduction Improvements (ANRI):
Construction for the Advanced Nutrient Reduction Improvements project is ongoing. The installation of conductors to all three new electrical buildings and new motor control centers continues. Rough-in of power and control raceways, wire pulling, and termination preparations continue for Primary Clarifier 5. Stress testing is continuing for Aeration Tank 6 with the newly installed design modifications. Primary gravity thickener mechanisms are being installed in both tanks.

SWIFT Facility:
The basin floors are being formed for the SWIFT Influent Pump Station and Recharge Well Backflush Equalization Tank. Pile driving for deep foundations for the SWIFT Facility site is ongoing and is expected to continue through May 2026. Pile driving hours will remain between 7:00 a.m. and 5:00 p.m., Monday through Friday, with Saturday pile driving hours being 8:00 a.m. to 4:00 p.m.  Preparation of the contractor's staging area, office complex, and access roads to the recharge wells on the SWIFT Facility site continues.  Installation of SWIFT Water supply and backflush lines for Recharge Wells 4, 5, 6, and 7 continues.  24-hour drilling will occur at Well 10 during the month of March; the drilling is not expected to cause any excess noise other than a hum from a generator. Stormwater improvements continue for Pond 1 and Pond 2.

Together, the overall goal of the Nansemond projects is to help support growth and protect future generations. To learn more about SWIFT or to schedule a tour of the SWIFT Research Center (located at HRSD’s Nansemond Treatment Plant in Suffolk, VA), please visit www.hrsd.com/swift/.

Project Cost: Approximately $952,000,000


Notices

 

October 2025 - Project Introduction

August 2025 - Construction Notice #1


alertSubscribe

"Tabb Pressure Reducing Station & Offline Storage Facility"
Tabb Pressure Reducing Station and Offline Storage Facility
HRSD Capital Improvement Program Project (YR010900)

 

Webpage Reviewed: April 2, 2026


HRSD is undertaking a project to construct the Tabb Pressure Reducing Pump Station and Offline Storage Facility, which will include constructing one 2.5-million-gallon offline storage tank and a pressure reducing pump station. The new facility will be located on HRSD property located at 900 Yorktown Road in Yorktown and is designed to relieve pressures to the sewer system during wet weather events and provide flow balancing for HRSD’s James River and York River Treatment Plants. The facility will improve system operations, increase flow capacity, and provide reliable sanitary sewer infrastructure for your community and the region. Additionally, these system improvements are mandated by the EPA to reduce sanitary sewer overflows.

There were several detailed comments about design features, drainage, safety, and odor control that are addressed in the FAQs. Several comments were related to project communications. HRSD is committed to maintaining an updated project web page with latest design and construction information for the duration of the project. If you wish to receive an email alert when the project website is updated, please subscribe at www.hrsd.com/subscriptions.

Project cost: $33,500,000



alertSubscribe

"Lucas Creek Pump Station Replacement"
Lucas Creek Pump Station Replacement
HRSD Capital Improvement Program Project (JR013500)

 

Webpage Reviewed: April 2, 2026


HRSD, your regional wastewater utility, is undertaking a project to replace its existing Lucas Creek Pump Station with a new pump station on an adjacent site. This effort will maintain the existing sanitary sewer service in the Denbigh Shores neighborhood while providing a modern, updated facility with improvements to noise, odor, and aesthetics. The new pump station will be styled to resemble a residential home, and it will contain all required equipment under a single structure. The multiple brick buildings that comprise the existing station will be demolished at the end of the project once the new pump station is in service.

Project Cost: $21.3 million

 


Notices

 

January 2026 - Construction Notice #9

November 14, 2025 - Construction Notice #8

October 2, 2025 - Traffic Advisory

September 2025 - Construction Notice #5

August 6, 2025 - Traffic Advisory

July 7, 2025 - Traffic Advisory

June 17, 2025 - Traffic Advisory

June 10, 2025 - Traffic Advisory

May 29, 2025 - Traffic Advisory

May 21, 2025 - Traffic Advisory

May 16, 2025 - Traffic Advisory

April 21, 2025 - Traffic Advisory


alertSubscribe

"Boat Harbor Treatment Plant Conversion and Transmission"
Boat Harbor Treatment Plant Pump Station Conversion 
Boat Harbor Treatment Plant Transmission Force Main Section 1 (Subaqueous)
Boat Harbor Treatment Plant Transmission Force Main Section 2 (Land)
HRSD Capital Improvement Program Project (BH015700, BH015710 & BH015720)

 

Webpage Reviewed: April 2, 2026


HRSD is closing its Boat Harbor Treatment Plant in Newport News to further reduce nutrients discharged to the James River Basin, which will support local water quality and Chesapeake Bay restoration efforts. A new pumping station facility will be constructed at the Boat Harbor location, and wastewater will be pumped to HRSD’s Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River. A significant portion of the treated water will undergo additional advanced treatment to meet drinking water quality standards to produce SWIFT Water™. To connect HRSD’s Boat Harbor and Nansemond facilities, construction of 31,000 feet of pipe is required. The pipe varies in size from 42 inches to 54 inches. The section installed under the Newport News Shipping Channel using horizontal direction drilling is 42 inches. The pipe then expands to 54 inches before reducing back down to 48 inches as the flow enters the Nansemond Treatment Plant for further treatment.

This work includes three separate projects: Boat Harbor Pump Station Conversion, Boat Harbor Underwater Transmission Pipe Installation, and Nansemond Treatment Plant Pipe Installation. To see more information, please check below in the “Update” section for a link to each project, including FAQ’s for each.

For more information on the SWIFT process, please visit www.hrsd.com/swift.


alertSubscribe

"Boat Harbor Pump Station Conversion"
Boat Harbor Treatment Plant Pump Station Conversion
Boat Harbor Treatment Plant Pump Station Conversion Site Improvements
HRSD Capital Improvement Program Project (BH015700 & BH015701)

 

Webpage Reviewed: April 2, 2026


As part of the Sustainable Water Initiative for Tomorrow (SWIFT) program, HRSD will pump wastewater from Newport News to its Nansemond Treatment Plant in Suffolk. At the Nansemond location, wastewater will be highly treated prior to discharge to the James River.  A significant portion of the treated water will undergo additional advanced treatment to produce SWIFT WaterTM which will meet drinking water quality standards. This will further reduce nutrients discharged to the James River Basin and support local water quality and Chesapeake Bay restoration efforts. The existing Boat Harbor Treatment Plant will be closed and replaced with the Boat Harbor Pump Station. 

Project Cost: Approximately $196.5 million


Notices

 

February 2026 - Traffic Advisory

October 2023 - Construction Notice Update #1

October 2023 - Notice to Neighbors